News from the City of Bend

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

For the latest City news, you've come to the right place.


Sign up to have the City news delivered right to your inbox.


LATEST NEWS


ALL CITY NEWS

North Interceptor Sewer Line Project June Update

Post Date:06/01/2020 12:17 PM

The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations and increase sewer capacity as part of the Community-supported Growth Plan.

The Project is broken up into three distinct Phases. Phase I is under construction and expected to be completed in Fall 2020. Phase II runs from the North Unit Main Canal near Pioneer Loop, through the City-owned Juniper Ridge property and across Hwy 97 to Clausen Road. 

Phase II construction will take place in three segments between June 2020 and Spring 2022.

  • Segment 1 – Pioneer Loop to City-owned Juniper Ridge property
  • Segment 2 – City-owned Juniper Ridge property
  • Segment 3 – BNSF railroad, across HWY 97, to Clausen Road

Join Us Online for a Virtual Open House!

In light of restrictions on public gatherings, the City of Bend invites you to attend a virtual open house for Phase II construction. This virtual open house is a platform for you to interact remotely with the City and its contractors. The open house features virtual exhibits and provides the opportunity to:

  • See the alignment in greater detail
  • Get answers to your questions
  • Learn more about what to expect during construction
  • Offer comments and feedback

To attend the virtual open house, visit the project website at www.bendoregon.gov/north-interceptor. The open house link is currently active and will remain active indefinitely. Please call the project team at 541-382-3264 if you have any questions or issues accessing the virtual open house website.

Upcoming Phase I Activities

  • Crews will begin installing 36” pipe for the Phase II connection near Pioneer Loop
  • Completion of erosion control in restored areas along Gentry Loop and Cricketwood Road
  • Installation of pumps, electrical equipment and interceptor discharge pipeline at the Water Reclamation Facility

An aerial photo of work crews using a crane to install a diversion manhole near Pioneer Loop.
Above: Work crews installing a diversion manhole near Pioneer Loop

Upcoming Phase II Activities

  • Initial construction work will begin on Segment 2 on June 1st. 
  • Crews will begin mobilizing equipment, clearing and removing vegetation, and preparatory excavation work in the southeast corner of the Juniper Ridge property. 
  • The Juniper Ridge Construction Zone (as shown on the map at the bottom of this notice) will be closed to all unauthorized access on June 22nd. Substantial construction work will commence at this time, including drilling and blasting, rock excavation, on-site material processing, installation of sewer pipe, and surface restoration. 
  • Additional construction notices specific to each work area will be sent to properties along the alignment prior to construction.
  • For additional information regarding the Juniper Ridge Construction Zone, including Frequently Asked Questions, please see the Juniper Ridge Construction Plan Update & FAQs.

A map depicting Phase II, Segments One through Three, the Juniper Ridge Construction Zone, and COID Pilot Butte main canal scheduled Summer 2020 through Spring 2022.
Above: A map depicting North Interceptor Sewer Project, Phase II – Segment 2

Thank you for your patience and cooperation during the design and construction of this important infrastructure project.

If you have questions or concerns, please call the project team at 541-382-3264 or visit our project website at www.bendoregon.gov/north-interceptor.

Accommodation Information for People with Disabilities

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic formats, and CD Formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at northinterceptorinfo@bendoregon.gov or 541-382-3264; Relay Users Dial 7-1-1, and 541-385-6676.

 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer

If you need assistance with any document, form, etc.,
you may request assistance from the Accessibility Program.