City of Bend
Home MenuAdmiral and King Jehu Sewer Project (COMPLETE)
The Admiral and King Jehu Sewer Project is the third construction phase of the Septic to Sewer Conversion Program.
Residents in these areas applied to the City of Bend to install public sewer in their neighborhoods. The areas approved for design and construction by the Septic to Sewer Committee are as follows:
- Admiral Way
- King Jehu Way and a portion of King Hezekiah Way
Gravity sewer mains and sewer laterals will be installed in each area to allow approximately 48 properties to decommission their septic systems and connect to the public sewer system.
More information about the Septic to Sewer Program (fees, other projects, permits, etc.) is available online at www.bendoregon.gov/septictosewerprogram.
This project is funded by the Clean Water State Revolving Fund (CWSRF).
PROJECT AREAS
TENTATIVE SCHEDULE
- Feb 25, 2021 - Septic to Sewer Committee Application Selection Meeting - Presentation
- Feb 2021 to early 2022 - Design
- Spring 2022 - Begin construction
- Winter 2022 - Complete construction
MEETINGS
February 24, 2022 Admiral and King Jehu Sewer Project Public Meeting
Presentation | Meeting Recording - Passcode: 12i^JnzN