14th Street Reconstruction Project (GO Bond)

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option


The 14th Street Reconstruction Project completed construction in October 2018. This project was the eighth and final project funded by the voter-approved transportation improvement General Obligation (GO) bond. The bond initially identified the project limits between Simpson and Galveston. However, City Council approved the extension for design to Newport Ave (north), and Donovan Ave (south). Funding was allocated for the construction of  Simpson to Albany (Zone 2), Albany to Galveston (Zone 3), and Newport to Galveston (Zone 4), between April and October 2018.




PROJECT
BACKGROUND


PROJECT
LOCATIONS
Construction icon.

PROJECT
UPDATES
Calendar icon.

CONSTRUCTION
SCHEDULE

PROJECT GOALS AND OBJECTIVES

  • Increase safety and mobility for all users and create an environment for walking, biking, and transit use.
  • Improve accessibility by removing or providing clearance from obstructions in the sidewalk.
  • Improvements result in a complete street with the Central Westside Plan (CWP) preferred land use scenario. The CWP land-use scenario proposes a mixed-use land use form projected to increase walking, biking, and transit trips, thereby reducing vehicle miles traveled.

PROJECT BACKGROUND

In 2016, the project team presented a GO bond program update to City Council, requesting authority to proceed with the 14th Street Reconstruction Project. Staff also proposed the extension of project limits due to lacking connectivity, sub-par infrastructure condition, transit planning efforts, recent development, and updated City planning efforts. City council provided authority during the January 20, 2016 meeting and requested staff present 30% level design and estimates upon completion.

Project limits extended north and south to include the following roadway segments:

  • NW 14th Street (NW Galveston Avenue to NW Newport Avenue)
  • SW Century Drive (SW Colorado Avenue to SW Simpson Avenue)

Project team staff presented the 30% design and project estimates to City council during the December 7, 2016 meeting. The presentation and council discussion focused on existing conditions, proposed improvements, class 4 estimates( feasibility/study phase), funding, and next steps. The next steps outlined a proposal to finalize design and outlined the estimated design fee range, schedule, and funding sources. City Council voiced support for continuing to final design for the entire length of the corridor, SW Colorado Ave to NW Newport Ave. Project team staff informed City Council that they would return with a contract amendment, including scope and fee, to complete the design.


PROJECT LOCATIONS

The project divided the corridor into four zones. View the completed typical sections for each zone below:

Map showing NW 14th Street/SW Century Dr construction between SW Colorado Ave and SW Simpson Ave.

ZONE 1:
Colorado Ave
to Simpson Ave
Map showing NW 14th Street/SW Century Dr construction between SW Simpson Ave and NW Albany Ave.

ZONE 2:
Simpson Ave
to Albany Ave
Map showing NW 14th Street/SW Century Dr construction between NW Albany Ave and NW Galveston Ave.

ZONE 3:
Albany Ave
to Galveston Ave
Map showing NW 14th Street/SW Century Dr construction between NW Galveston Ave and NW Newport Ave.

ZONE 4:
Galveston Ave
to Newport Ave

 
ZONE 1 - Colorado to Simpson (in Phase II of the construction schedule) 

Zone 1 typical section diagram: 14th Street from Colorado Avenue to Simpson Avenue.

The proposed Zone 1 typical section extends from the intersection of SW Colorado Avenue to SW Simpson Avenue. The depiction of the typical section includes a three-lane section with a two-way turn lane, two 11-foot travel lanes, two 7-foot buffered bike lanes, planter strips, and an 8 to 10 foot sidewalk on each side of the corridor.

(100% Design Exhibit)

 

ZONE 2 - Simpson to Albany (in Phase I of the construction schedule) 

Zone 2 typical section diagram: 14th Street from Simpson Avenue to Albany Avenue.

The proposed Zone 2 typical section extends from the intersection of SW Simpson Avenue to NW Albany Ave. The depiction of the typical section includes a three-lane section with a two-way turn lane, two 10.5-foot travel lanes, two 7-foot buffered bike lanes, planter strips, and an 8 to 10-foot sidewalk on each side of the corridor.

(100% Design Exhibit) 

 

ZONE 3 - Albany to Galveston (in Phase II of the construction schedule) 

Zones 3 typical section diagram: 14th Street from Albany Avenue to Galveston Avenue.

The proposed Zone 3 typical section extends from the intersection of NW Albany Avenue to NW Galveston Avenue. The depiction of the typical section includes a two-lane section with two 10.5-foot travel lanes, two 7-foot buffered bike lanes, planter strips, and a 6 foot sidewalk on each side of the corridor.

(100% Design Exhibit)

 

ZONE 4 - Galveston to Newport (in Phase I of the construction schedule) 

Zones 4 typical section diagram: 14th Street from Galveston Avenue to Newport Avenue.

The proposed Zone 4 typical section extends from the intersection of NW Galveston Avenue to NW Newport Avenue. The depiction of the typical section includes a two-lane section with two 10.5-foot travel lanes, two 7-foot buffered bike lanes, planter strips, and a 6-foot sidewalk on each side of the corridor.

(100% Design Exhibit) 


PROJECT UPDATES

  • 14th Street and General Obligation Bond Project Completion

    The City invites media, neighbors and area businesses to join in celebrating the completion of the 14th Street corridor improvement project at 3:30 p.m. on Friday, Oct. 19, 2018, in the parking lot at Parrilla Grill (635 NW 14th Street).

    10/15/2018 11:55 AM

  • Construction is nearing completion in this area. with concrete work, paving, and landscaping the main tasks to finish.

    Concrete work, paving, and landscaping are main tasks to finish.

    10/08/2018 2:45 PM

  • End in sight for 14th Street work

    Crew are busy

    10/01/2018 11:26 AM

  • The 14th Street Reconstruction project, is in its final stage!

    09/24/2018 1:17 PM

  • Sept 14th Update

    09/17/2018 5:55 PM

  • September - October Construction Update

    09/10/2018 10:09 AM

  • Complete closure of 14th Street from NW Baltimore Av to NW Galveston Av

    08/31/2018 4:36 PM

  • Northbound lane of 14th Street is closed on the NW Albany Av to Galveston Av segment

    08/28/2018 12:49 PM

  • Remaining Project Schedule Highlights

    8/10/18 Week of August 13th: Paving crews will be on-site between Newport Av and Galveston Av beginning Monday morning, August 13th. Paving and striping activities will take place throughout the week with the re-opening currently scheduled for end of day, Friday the 17t

    08/10/2018 3:36 PM

  • Open House - August 6th

    8/3/18 - Open House Reminder: The City of Bend will host an open house at the Westside Village Magnet School, 1101 NW 12th Street, Monday evening August 6, from 5:30 – 7 pm. Information and graphics will be presented regarding Phase 2 construction of 14th Street, the segment between NW Galveston A

    08/03/2018 4:35 PM

  • Re-opening of the southbound lane of 14th Street between Newport Ave. and Galveston Ave.

    Open House Reminder: The City of Bend will host an open house at the Westside Village Magnet School, 1101 NW 12th Street, Monday evening August 6, from 5:30 – 7 pm. Information and graphics will be presented regarding Phase 2 construction of 14th Street, the segment between NW Galveston Av and NW

    07/27/2018 5:36 PM

  • Phase 2 portion of the 14th St. Reconstruction project - Expected to start August 6th

    The City will be hosting an open house on August 6, from 5:30 to 7pm at the Westside Village School, 1101 NW 12th Street.

    07/24/2018 9:17 AM

  • Project Update

    14th Street reconstruction work is well underway the segment between Galveston Av and Newport Av. The complete closure of this segment requires renewed driver awareness of the designated detours. Residential areas are our safety focus as traffic patterns continue to change. The contractor’s intent

    07/11/2018 4:12 PM

  • Schedule Change

    July 2, 2018, SCHEDULE CHANGE: 14th Street reconstruction work has shifted to the segment between Galveston Av and Newport Av. The complete closure of this segment is now scheduled to begin Monday July 2.

    07/02/2018 2:40 PM

  • Night time work beginning Sunday night June 24th.

    June 22, 2018 Final lift paving along the entire 14th Street corridor between Simpson Av and Albany Av is still on schedule for night time work beginning Sunday night June 24th. Striping will follow the next few nights. Late night delays should be expected.

    06/26/2018 3:26 PM

  • Albany - 14th St - Work has begun

    Work on Albany/14th Street has begun. The Albany/14th Street intersection work is scheduled to be completed next Friday, June 22. Final lift paving is scheduled for night time work beginning June 25th.

    06/15/2018

  • Open House - June 5th

    Please attend the Open House on June 5 for more information. Meeting Date: Tuesday, June 5th, 5:00 – 6:30 pm Rosie Bareis Community Campus, 1010 NW 14th Street

    06/10/2018

  • May 25, 2018 Project Updates

    Access to Knoll Avenue businesses between 14th and 15th Street is currently from 15th Street; this is while crews work on waterline replacements and improvements on Knoll Avenue and the intersection.

    05/25/2018 5:53 PM

  • May 17, 2018 Project Updates

    May 17, 2018 Access to Knoll Avenue Businesses between 14th Street and 15th Street is currently from 15th Street, while crews work on waterline replacements and improvements on Knoll Avenue and the intersection

    05/22/2018

  • May 14, 2018 Project Updates

    The Simpson Avenue/14th Street roundabout is scheduled to be re-open next Monday, May 14, 7 a.m. The roundabout will be open to all traffic except the entering leg from southbound 14th Street.

    05/14/2018

  • May 4, 2018 Project Updates

    The roundabout at Simpsons Avenue and 14th Street is still on schedule to reopen the week of May 14th. Concrete work is in process and will be followed with new asphalt, tying the two surfaces together.

    05/04/2018 12:30 PM

  • April 26, 2018 Project Updates

    The great Spring weather is enabling the construction crews to complete various tasks ahead of schedule. Look for the potential reopening of the Simpson Roundabout as early as the week of May 14. Great job K&E and Roger Langliers Construction.

    04/26/2018 6:05 PM

  • Week of April 23, 2018 Project Update

    Access to businesses along 14th St and Simpson Ave will remain open during construction. Driveways under construction are indicated by blue markers and signs. Drive cautiously and respectfully when navigating the construction zone.

    04/23/2018

  • Week of April 9 2018 Project Updates

    Updates for the 14th Street project The Simpson Av./Century Dr. Roundabout is expected to be fully closed on April 9. It is projected to reopen in mid-May.

    03/29/2018 6:05 PM

  • Week of April 16, 2018 Project Updates

    Simpson Roundabout closure is in place. Please note detour routes for traveling through and around the construction zone. It is projected to reopen in mid-May.

    03/29/2018 6:05 PM

  • 3/26/18 Project Updates

    Cascade Natural Gas (CNG) will begin construction at 14th St between Newport & Galveston - Southbound traffic along 14th restricted (approx 10 weeks) 4/2/18 - Construction scheduled for the Albany to Simpson Roundabout corridor - Completed by July 1, 2018

    03/23/2018 3:18 PM

 


CONSTRUCTION SCHEDULE

CENTURY DRIVE  - SIMPSON TO ALBANY

Fall 2018

Tree planting

 

14TH STREET - GALVESTON TO NEWPORT

July 2 – July 30

14th Street from Galveston to Newport, Full closure of roadway for construction.

July 31 – August 3

Closure of the Southeast quadrant of the Newport Avenue Roundabout at 14th Street.  Detours in place for Newport eastbound traffic.

July 31 – August 5

14th Street from Galveston to Newport, southbound lane reopens temporarily, northbound lane remains closed.

August 6 – August 18

14th Street from Galveston to Newport, Full closure of roadway for construction.

 August 19 – September 28 14th Street form Galveston to Newport, road reopens, various minor components of work remain under construction with intermittent flagging and minor delays.

 

14TH STREET – ALBANY TO GALVESTON

August 6 – August 19

Flagging for waterline crossing work, expect delays.

August 20 – September 3

14th Street from Albany Ave to Galveston Ave, east side (northbound lane) of roadway closed for construction.

September 4 – October 31

14thStreet from Albany Ave to Galveston Ave, Full closure of roadway for construction.

Footer Broken Top Three Sisters

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer

If you need assistance with any document, form, etc.,
you may request assistance from the Accessibility Program.