Via Sandia/East Lake/Orion Drive Sewer (COMPLETE)

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option
A photo of an excavator excavating within a fenced barricade in a residential neighborhood with pine trees in the background.

The Via Sandia/East Lake Drive/Orion Drive Sewer Project is the second construction phase of the Septic to Sewer Conversion Program.  This project was completed in August 2021.


Residents in these areas applied to the City of Bend to install public sewer in their neighborhoods. The areas approved for design and construction by the Septic to Sewer Committee are as follows:

  1. Via Sandia and Cabin Court
  2. East Lake Drive and a small portion of Twin Lakes Loop
  3. A portion of Orion Drive

Gravity sewer mains and sewer laterals will be installed in each area to allow approximately 40 properties to decommission their septic systems and connect to the public sewer system.

More information about the Septic to Sewer Program (fees, other projects, permits, etc.) is available online at www.bendoregon.gov/septictosewerprogram.

The United States Environmental Protection Agency logoThe Oregon Department of Environmental Quality logo
This project is funded by the Clean Water State Revolving Fund (CWSRF).


PROJECT AREAS

Via Sandia Neighborhood Map

East Lake Neighborhood Map

Orion Neighborhood Map

TRAFFIC IMPACT LOCATIONS


Construction is complete as of August 2021.


MEETINGS

Past Meetings:

 February 11, 2021 - Via Sandia, East Lake, and Orion Sewer Project Public Meeting - Presentation

No results found.
Please correct the fields below:

1
Name
Name
2
Email Address
 *
  1. To receive a copy of your submission, please fill out your email address below and submit.
    Footer Broken Top Three Sisters