City of Bend
Home MenuAwbrey Butte Waterline Improvement Project
REMINDER: PORTLAND AVENUE FULL CLOSURE BEGINS TUESDAY, NOV 12, 2024 - SPRING 2025
USE NEWPORT DETOUR AT 9TH AND WALL STREETS (DETOUR MAP)
See additional details below.
This project will provide water distribution system upgrades to the Awbrey Butte area with eight interrelated water improvement subprojects and a portion of the adjacent Portland Avenue Improvements.
PHASE 2 - ACTIVE CONSTRUCTION
Phase 2 work began in January 2024 and includes subprojects 2, 7, and 8. Each subproject has specific construction details and traffic changes outlined below. The schedule is subject to weather conditions.
Remaining construction will occur within the Public Right of Way and will entail trenching, rock excavation, installation of pipes, fittings, valves, water meters, and surface restoration. Before construction activities begin in your neighborhood, residents will receive a notification providing specific information regarding construction impacts. Please be advised of Franchise Utility relocations taking place ahead of the planned Awbrey Butte Waterline Improvements.
Selective sewer and stormwater improvements, as well as a portion of the voter-approved 2020 Transportation GO Bond Portland Avenue Improvements are being constructed as part of the Awbrey Butte Waterline Improvement Project to take advantage of synergy opportunities.
SUBPROJECT 2 - PORTLAND AVENUE & BRIDGE
Stages 2 & 3 Improvements November 2024 through Spring 2025
Stage One of the waterline improvements on the Portland Avenue Bridge has concluded.
Between Nov. 12, 2024 through Spring 2025, Stages 2 and 3 of the improvements will continue with the installation of a new waterline along Portland Avenue from Steidl Road to Ninth Street. Residents will receive notifications providing detailed information about the construction's impacts. Franchise utility work, asphalt, and concrete restoration work are anticipated periodically from summer 2024 through spring 2025.
Stage 2 and 3 traffic will be restricted to local access only, managed by flaggers, with closures implemented two blocks at a time to minimize disruption. Traffic will be routed to Newport Avenue via 9th and Wall streets, and local and emergency vehicle access will be maintained.
The schedule is weather dependent, with periodic asphalt and concrete restoration work expected through Spring 2025.
SUBPROJECT 8 - NEW AWBREY TRANSMISSION MAIN
Mid-January 2024 through Spring 2025
Subproject 8 improvements are being implemented in multiple stages to minimize traffic impacts. Local access and access for emergency vehicles will be maintained. Work is progressing to the next segment, which involves installing 8-inch and 30-inch waterline pipes, as well as stormwater facilities and stormwater trunk main. This work is taking place along Saginaw Avenue, Juniper Street, Trenton Avenue, 12th Street, and into Hillside Park.Stage 1 - Shevlin Park Road - COMPLETE
The Mt. Washington and Shevlin Park Road roundabout is open to all traffic, and construction activities along Shevlin Park Road are complete.
Stage 2 - College Way and Saginaw Avenue
The second phase of Subproject 8 water main construction required a full closure of NW College Way at Saginaw Avenue. Crews will return periodically for the installation of additional pipe and for asphalt and concrete restoration work through Spring 2025.
SYNERGY
There are some selective opportunities for stormwater improvements that will be adjacent to the waterline improvements. There are some selective opportunities for stormwater improvements that will be adjacent to the waterline improvements and a portion of the voter-approved 2020 Transportation GO Bond Portland Avenue improvements. Learn more about the Portland Avenue Project.
TENTATIVE PROJECT SCHEDULE
Description |
Begin |
End |
Contractor and Engineer Selection |
Fall 2021 |
May 2022 |
Design Work |
June 2022 |
|
Construction |
Spring 2023 |
Spring 2025 |
Tentative Design Schedule by Subproject:
- Subprojects 1, 3, 4, 5, & 6: September 2022 - fall 2023
- Subprojects 2, 7, 8, & 9: November 2022 - spring 2024
Tentative Construction Schedule by Subproject:
- Subproject 1: June 2023 – fall 2023
- Subproject 2: early 2024 – summer 2024
- Subproject 3: September - October 2023
- Subproject 4: November - December 2023
- Subproject 5: November 2023 – spring 2024
- Subproject 6: October - November 2023
- Subproject 7: early 2024 – fall 2024
- Subproject 8: early 2024 – winter 2025
- Subproject 9: early 2024 – fall 2024