Admiral & King Jehu Sewer Project Update – July 11, 2022
TENTATIVE CONSTRUCTION ACTIVITIES FOR ADMIRAL WAY
- Rock hammering continues on Admiral Way.
- Admiral Way is closed to thru-traffic. Local access to residences is provided. Please refer to the detour map below.
- Lateral staking should now be current or pending relocation if you have been communicating directly with the project contact. Please reach out to the project contact if you still feel your lateral is not in the correct location.
- Construction survey staking is ongoing; please do not move or remove any wooden survey stakes.
- Minor tree trimming and clearing in the right of way for the main line or lateral installation will continue as needed. At the end of the project, the crews will tidy anything that was cleared or trimmed and still looks “rough.”
TENTATIVE CONSTRUCTION ACTIVITIES FOR KING JEHU WAY & KING HEZEKIAH WAY
- Paving is scheduled for Friday, July 15 on King Jehu Way.
- PLEASE PLAN TO PARK YOUR VEHICLES OUTSIDE OF THE CONSTRUCTION ZONE ON THIS DAY. VEHICLES NEED TO BE MOVED OUT OF THE CONSTRUCTION ZONE BY 7:00 AM ON FRIDAY, JULY 15.
- You will be unable to drive on the roadway during paving activities. You will be able to drive on the roadway once paving is completed on Friday evening, at approximately 6:00 PM.
- Door flyers will be delivered a minimum of 48 hours in advance.
- Landscape restoration on both King Hezekiah and King Jehu will occur over the next couple of weeks after paving is complete. As a reminder, items that will be replaced include bark mulch, rock mulch, cinders, sod, timbers, and any mailboxes or irrigation lines that were disturbed during construction. Items in the right-of-way that will not be restored include fences, rock walls, concrete borders, pavers, trees that were identified for removal, and plants/bushes/flowers other than sod that were impacted.
- The final cleanup will be ongoing after paving. Any mailboxes that were shifted during construction will be returned to their original location.
- Road base preparation is ongoing this week on King Jehu.
- Traffic control measures will remain in place until King Jehu is paved and all pipe testing is complete.
- The Notice of Operational Completion (NOC) letters are anticipated to be mailed out approximately by the end of the month.
PROJECT PHOTO
Below is a photo of the roadway paving on King Hezekiah.

TRAFFIC CONTROL
The maps below show the closure area (solid red line) and detour (blue dashed line). Local access will be provided for homeowners living on the closed streets. You may experience minor delays when driving through the construction zone. If an excavator is in the way, make eye contact or wave, and they are typically good at moving out of the way to let traffic pass. Please proceed with caution when driving in the construction zone. We appreciate your ongoing patience.
Admiral Way Detour

King Jehu/King Hezekiah Detour

RESOURCES
- Information specific to the construction of the Admiral and King Jehu Sewer Project is available online at www.bendoregon.gov/admiral-king-jehu.
- Information on the Septic to Sewer Program (fees, other projects, permits, etc.) is available online at www.bendoregon.gov/septictosewerprogram.
PROJECT CONTACT
- Alex Doza, P.E., Assoc. DBIA | City of Bend, Project Engineer – adoza@bendoregon.gov or 541-678-2597
Thank you for your ongoing patience as we complete this important project!