Admiral & King Jehu Sewer Project Update – May 23, 2022

TENTATIVE CONSTRUCTION ACTIVITIES (KING HEZEKIAH WAY & KING JEHU WAY)

  • In general, construction sequencing will begin on King Hezekiah Way, followed by King Jehu Way, and then on Admiral Way.
  • Locate markings are painted on the ground, indicating where underground utilities are located. These markings are constantly being refreshed due to the excavation activities. You may see locate surveyors on-site on a regular basis.
  • Survey staking is ongoing on King Jehu and Admiral Way; please do not move or remove any wooden survey stakes.
  • Minor tree trimming activities and clearing will occur as needed. At the end of the project, the crews will tidy anything that was cleared or trimmed and still looks “rough”.
  • Pre-hammering for the sewer main is ongoing on King Jehu and should be complete in the next few days. 
  • Sewer main installation will begin on King Jehu this week.
  • Sewer main and lateral installations are complete on King Hezekiah; Activities to prepare for road restoration are occurring.
  • Franchise utilities are relocating their facilities as needed concurrent with sewer construction activities.
  • Traffic control measures remain in place.
  • In observance of Memorial Day, no work will occur on May 30.

PROJECT PHOTO

Below is a photo showing what a completed sewer service lateral looks like. The lateral connects to the sewer main line and extends to the edge of the right-of-way. This is where your plumber will connect your plumbing once the project is complete. The green PVC will be cut and capped to surface grade, and the marker will remain in place behind it for easy locating. Restoration will occur for items including sod, irrigation, bark mulch, rock mulch, cinders, and timbers/railroad ties.

A photo of a completed sewer service lateral before it's cut and capped to surface grade.

TRAFFIC CONTROL

Traffic control signs have been staged and are ongoing on King Hezekiah and King Jehu. The map below shows the closure area (solid red line) and detour (blue dashed line). Local access will be provided on King Jehu Way, Hezekiah Way, and King Solomon Court for homeowners living on those streets. Please proceed with caution when driving in the construction zone.

A map of the traffic control plan depicting the road closure on King Hezekiah & King Jehu, and the detour route on King Hezekiah & King David.

Road Closed to Thru Traffic / Local Access Only

Local traffic (meaning homeowners who live adjacent to the construction zone) can drive past this sign to access their driveways/homes. Please use extreme caution when driving in the construction zone. Make eye contact with the equipment operators so that you know it is safe to pass. We appreciate your ongoing patience.

A photo a barricade, cones, and road signs marking the road closure to thru traffic and local access only.

RESOURCES

PROJECT CONTACT

Alex Doza, P.E., Assoc. DBIA | City of Bend, Project Engineer – adoza@bendoregon.gov or 541-678-2597