Thank you for your interest in the Murphy Corridor Improvements Project.

The Brosterhous Rd roundabout will be open to traffic the week of April 6, weather dependent. Intermittent flagging should be expected as construction work continues around the Brosterhous Rd & Murphy Rd intersection. The temporary two-lane bypass road will be removed following the opening of the roundabout.

Expect to see crews working in the Brosterhous Rd & Murphy Rd roundabout area through early May as we complete this phase of the project.

Construction activities for the upcoming week

  • Crews are continuing to prep and pour sidewalks and curbs
  • Construction will begin on the retaining wall
  • Road striping work will be completed
  • Removal of the current temporary two-lane bypass road

Upcoming Construction Traffic Control

Modernization improvement work between Brosterhous Rd and Country Club Dr will begin the week of April 6 and is expected to be completed by the end of August. See the graphic below for depiction.

Stage 1 (April 6-mid April):

  • Construction of a temporary two-lane bypass road on the north side of Murphy Rd. The bypass road will connect to Murphy Rd to accommodate traffic around the construction area.
  • Expect intermittent flagging

Stage 2 (Late April-Late June):

  • Two-way traffic on the temporary bypass road
  • Expect intermittent flagging during construction of roadway & utilities

Stage 3 & 4 (Late June-Late August):

  • Westbound traffic detour on Murphy Rd, between Brosterhous Rd and Country Club Dr
  • Eastbound traffic on Murphy Rd will be maintained
  • Expect intermittent flagging

A graphic depicting the next stage of work between Brosterhous Rd and Country Club Dr constructing a 3-lane roadway with bike lanes, sidewalks and safe crossings from early April through late August 2020.
Above: Graphic depicting the next phase of work between Brosterhous Rd and Country Club Dr

Changes to Construction Zones

  • The Brosterhous roundabout will open next week, and the bypass road will be removed as mentioned above.
  • Brown Trout Pl open to right-in/right-out traffic with the Brosterhous opening. Please note, Brown Trout Pl will be closed at Murphy Rd again in June, when westbound Murphy Rd traffic is detoured.
  • A temporary two-lane bypass road will be constructed on the north side of Murphy Rd beginning April 6.

Current Road Closures (in place until roundabout opens)

  • Northbound and southbound traffic on Brosterhous Rd is closed at Murphy Rd.
  • Brown Trout Pl is closed to traffic at Murphy Rd.
  • A temporary two-lane bypass road is open at the southwest corner of Brosterhous Rd, connecting to Murphy Rd to accommodate traffic around the construction area.

An interactive map of closures and detours can be found at www.bendoregon.gov/traffic.

Please contact the project team with concerns, comments, and questions at (541) 322-9919.

An aerial photo of the Murphy/Brosterhous roundabout looking south over work crews, equipment, surrounding neighborhoods, and a landscape of pine trees and hills in the background.
Above: View of the Murphy/Brosterhous roundabout looking south

Accommodation Information for People with Disabilities

Sign language interpreter service, assistive listening devices, materials in an alternate format such as Braille, large print, electronic formats, and CD Formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at MurphyProjectTeam@bendoregon.gov or (541) 322-9919; Relay Users Dial 7-1-1, and (541) 385-6676.

View All News