Neff and Purcell Improvement Project Update – January 30, 2024
The opening of the Purcell Boulevard extension is anticipated on Friday, February 2 by the end of the business day. Some additional restoration work may continue after February 2, with minor traffic impacts.
CONSTRUCTION ACTIVITIES – January 30- February 2
Purcell Extension
- Concrete and landscape work continues, expect shoulder work and flaggers.
- Roadway closures continue through February 2. Crews and equipment will be working within the roadway. Please follow signed detour routes.
Neff and Purcell Intersection
- Installation of irrigation and landscaping continues, expect shoulder work and lane shifts.
- Some landscape plantings and restoration following construction may occur in the spring due to weather.
Please note: Dates are estimates and subject to change.
ROAD CLOSURES AND DETOURS
- Neff and Purcell Intersection expect single lane closure with flagging.
- The Purcell Extension closures and detours will continue through February 2. Please use signed detour routes.
Interactive Traffic Impacts Map
You may also monitor other detours and closures at bendoregon.gov/traffic.
QUESTIONS AND COMMENTS?
- Project Phone Line: (458) 202-7348
- Project Email: neffpurcell@bendoregon.gov
- Project Website: bendoregon.gov/neff-purcell
- Project Engineer: Drew Wells, PE
This project is partly funded by the voter-approved 2020 Transportation General Obligation (GO) Bond. To learn about more projects around Bend included in the GO Bond, visit bendoregon.gov/gobond.
View All News