Neff and Purcell Improvement Project Update – October 13, 2023
SAFETY FIRST
Heavy machinery and equipment are very active throughout the work zone and nearby roadways. Slow down, obey flaggers and signs, and use designated detour routes. Crews will be working Saturday, October 14.
CONSTRUCTION UPDATE
Electrical components installed for traffic signal pole at northwest corner of Neff and Purcell (facing east)
CONSTRUCTION ACTIVITIES – October 14 –20
Neff and Purcell Intersection
- Grader work in preparation for roadway paving.
- Concrete preparation work for new curbs continues. Crews will work Saturday, October 14.
- Traffic signal installation work continues.
- Sidewalk demo and replacement on Purcell Boulevard continues. Residents with impacted driveways will receive notice.
- The franchise utilities, such as gas, power, cable, etc., are progressing towards completion of relocating facilities to their ideal locations and depths.
- Utility relocation near Cliff Drive and Neff Road continues.
Purcell Extension
- Installation of the new crosswalk illumination continues
- Pouring of curb on east side of Purcell Boulevard
- Preparation work for sidewalks begins
RESOURCES
Commute Options
- Commute Options is here to help you with transportation options during construction. Join the Neff/Purcell Improvement Project network on Get There Connect to match up in a carpool, explore your transit, biking, walking options, help reduce traffic and more! Sign up today and learn more about your chance to win a $50 gift card! Visit Commute Options for more information.
Project Communications
- The City is committed to keeping neighbors, businesses and the community informed throughout the project through public informational meetings, mailings, emails and the project website. For more information, contact the project team at neffpurcell@bendoregon.gov.
- Please contact us if you need any additional materials that would be helpful to spread the word to your patients, clients, customers and delivery personnel regarding detouring and closures.
- Share the website information where others can also sign up for updates: bendoregon.gov/neff-purcell
ROAD CLOSURES AND DETOURS
Neff and Purcell Intersection Detour Routes
- Eastbound (south option) – go south on Eighth Street, east on Greenwood Avenue, north on 27th Street
- Eastbound (north option) – go north on Eighth Street, east on Butler Market Road and south on 27th Street
- Westbound (south option) – go south on 27th Street, west on Greenwood Avenue, north on Eighth Street
- Westbound (north option) – go north on 27th Street, west on Butler Market Road and south on Eighth Street
Temporary Pedestrian Access Routes
Please use marked temporary pedestrian detours. Please be aware these temporary pedestrian access routes will change as needed during different phases of work.
Interactive Traffic Impacts Map
You may also monitor current and upcoming detours and closures at bendoregon.gov/traffic.
QUESTIONS AND COMMENTS?
- Project Phone Line: (458) 202-7348
- Project Email: neffpurcell@bendoregon.gov
- Project Website: bendoregon.gov/neff-purcell
- Project Engineer: Drew Wells, PE
This project is partly funded by the voter-approved 2020 Transportation General Obligation (GO) Bond. To learn about more projects around Bend included in the GO Bond, visit bendoregon.gov/gobond.
View All News