Newport Corridor Improvements Project Update – June 24, 2022
SAFETY FIRST
Pedestrians should follow all designated routes around the newly formed curbs and sidewalks. The exterior of the concrete may appear dry but could still be curing beneath the surface.
CONSTRUCTION UPDATE
Newport Avenue from 10th Street to 12th Street is scheduled to be open to the public on Friday, July 1, 2022.
- Newport Avenue will temporarily open to traffic from Friday, July 1 until Tuesday, July 5.
- Wednesday, July 6, Newport Avenue will be closed again for construction (12th Street up to the 14th Street roundabout).
Newport Avenue Scheduled Construction – (Juniper Street to College Way)
- Landscaping will continue near sidewalks and planters.
- There may be intermittent flagging and lane shifts while crews finalize the landscaping.
Newport Avenue Scheduled Construction – (10th Street to 12th Street)
- Forming of the concrete driveway aprons and sidewalks.
- Begin pouring concrete for the driveway aprons and sidewalks.
- Curing of the concrete will begin and takes roughly 5 to 7 days.
- The final grading of Newport Avenue begins in preparation for Asphalt.
DETOURS IN EFFECT
Traffic Closures and Changes
- Newport Avenue, west of 10th Street to 12th Street, is closed.
- 11th Street, north and south of Newport Avenue, will be local access only.

Access to all businesses along Newport Avenue will be open through construction.
Temporary Pedestrian Accessibility Route for Segment 2B Construction
If heading eastbound on Newport Avenue:
- At the east side of 12th Street, head southbound to Milwaukee Avenue.
- Turn left on the north side of Milwaukee Avenue to travel eastbound.
- Cross 11th Street and continue to the west side of 10th Street.
- Turn left on 10th Street to travel north to Newport Avenue.
- Turn right on Newport Avenue, crossing 10th Street to continue traveling eastbound.
If heading westbound on Newport Avenue:
- At the west side of 10th Street, head south to Milwaukee Avenue.
- Turn right to travel west down the northside of Milwaukee Avenue.
- Cross 11th Street and continue on Milwaukee Avenue to 12th Street.
- At the west side of 12th Street, turn right to travel northbound to get back onto Newport Avenue and turn left to continue traveling westbound.
GENERAL PROJECT NOTES
- Access to all area businesses along the construction corridor will be maintained.
- Please do not enter the construction zone before, during, or after hours.
- Daytime work hours are in effect from 7:00 AM – 6:30 PM.
- The ‘Tree Preservation and Removal Overview Exhibits’ can be found on the project website. These exhibits provide design details about each tree being removed and where new trees will be planted.
- There are many construction projects in the area and throughout the City of Bend. Travel safely.
PROJECT COMMUNICATIONS
- EMS, buses, and other delivery/service providers have been included in the project updates distribution list.
- Please help us spread the word to your clients, customers, and delivery personnel regarding detouring and closures.
- Share the project website (provided below), where others can also sign up for project updates.
- Please contact the project team if you are not the correct contact for your organization or if others need to be included.
QUESTIONS OR COMMENTS?
Project Website: https://www.bendoregon.gov/newportimprovements
24-Hour Construction Phone Line: 541-200-6972
Project Contacts:
Brittany Barker, PE – City of Bend Principal Engineer – bbarker@bendoregon.gov
Peter Guth, Project Public Involvement Coordinator – pguth@dowl.com or 548-256-6007