Newport Corridor Improvements Project Update – June 3, 2022
SAFETY FIRST
Saturday, June 4, there will be construction during typical work hours as crews prepare the subgrade for concrete curbs.
Pedestrians should follow designated paths and crossings. Pedestrian crossings are subject to change throughout the course of construction. When near the construction site, be aware of equipment and construction crews as they are constantly on the move.
CONSTRUCTION UPDATE FOR JUNE 2 – JUNE 9

Above: Sub-grading is underway along 11th Street
Newport Corridor Improvements Scheduled Construction – Segment 5 (Juniper Street to College Way)
- Landscaping will continue near sidewalks and planters.
Newport Corridor Improvements Scheduled Construction – Segment 2B (10th Street to 12th Street)
- Connection of water services to the newly installed water main pipe.
- Subgrade and curb preparations begin.
- Continue stormwater system replacement on 11th Street and Newport Avenue
- Concrete is poured for the stormwater inlet structures.
DETOURS IN EFFECT
Traffic Closures and Changes
- Newport Avenue, west of 10th Street to 12th Street, is closed.
- 11th Street, north and south of Newport Avenue, will be local access only.

Access to all businesses along Newport Avenue will be open through construction.
Temporary Pedestrian Accessibility Route for Segment 2B Construction
If heading eastbound on Newport Avenue:
- At the east side of 12th Street, head southbound to Milwaukee Avenue.
- Turn left on the north side of Milwaukee Avenue to travel eastbound.
- Cross 11th Street and continue to the west side of 10th Street.
- Turn left on 10th Street to travel north to Newport Avenue.
- Turn right on Newport Avenue, crossing 10th Street to continue traveling eastbound.
If heading westbound on Newport Avenue:
- At the west side of 10th Street, head south to Milwaukee Avenue.
- Turn right to travel west down the northside of Milwaukee Avenue.
- Cross 11th Street and continue on Milwaukee Avenue to 12th Street.
- At the west side of 12th Street, turn right to travel northbound to get back onto Newport Avenue and turn left to continue traveling westbound.
GENERAL PROJECT NOTES
- Access to all area businesses along the construction corridor will be maintained.
- Please do not enter the construction zone before, during, or after hours.
- Daytime work hours are in effect from 7:00 AM – 6:30 PM.
- The ‘Tree Preservation and Removal Overview Exhibits’ can be found on the project website. These exhibits provide design details about each tree being removed and where new trees will be planted.
- There are many construction projects in the area and throughout the City of Bend. Travel safely.
PROJECT COMMUNICATIONS
- EMS, buses, and other delivery/service providers have been included in the project updates distribution list.
- Please help us spread the word to your clients, customers, and delivery personnel regarding detouring and closures.
- Share the project website (provided below), where others can also sign up for project updates.
- Please contact the project team if you are not the correct contact for your organization or if others need to be included.
QUESTIONS OR COMMENTS?
Project Website: https://www.bendoregon.gov/newportimprovements
24-Hour Construction Phone Line: 541-200-6972
Project Contacts:
Brittany Barker, PE – City of Bend Principal Engineer – bbarker@bendoregon.gov
Peter Guth, Project Public Involvement Coordinator – pguth@dowl.com or 548-256-6007
View All News