SW Sewer Basin Phase 2B Project Update – February 28, 2022

SAFETY FIRST

Please be aware of construction activities and drive carefully through the work zone, including open-trench excavation. Open trenches are fenced off at the end of each day. 

CONSTRUCTION UPDATE

Week of February 28 Construction Activities

  • Crews will continue excavating and installing sewer service lines towards existing pump stations that will be decommissioned along McMullin Drive. This construction includes partial road closures and detours.
  • Crews will continue excavating existing curbs and roadways along Romaine Village Way, Ridge Drive, and Cinder Lane for new curbs and grade work for new roadways. This construction includes partial closures and detours. 
  • Crews have begun the installation of pipes for the stormwater facilities along the alignment on Ridge Drive, Cinder Lane, and McMullin Drive. This construction includes partial closures and detours.

DETOURS IN EFFECT

  • A portion of the streets mentioned above may be closed for grading and sewer construction activities. Please follow the necessary road closed and detour signs.
  • Flaggers will be present for the construction activities as needed.

An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic.

PROJECT COMMUNICATIONS 

General Project Notes

  • Access to all businesses located at the end of Romaine Village Way will be maintained.
  • Emergency access will be maintained throughout construction.

QUESTIONS OR COMMENTS?

Project Website: https://www.bendoregon.gov/swsewerpipe

Project Contact: Jake Sherman, Senior Project Engineer – Phone: 541-383-4882 | Email: jsherman@bendoregon.gov

A photo of the wet well removed at the existing pump station.
Above: Removal of wet well at existing pump station

A photo of work crews and excavation equipment excavating a trench for new storm pipe to the maintenance hole.
Above: Excavation for new storm pipe to maintenance hole