SW Sewer Basin Phase 2B Project Update – February 7, 2022
SAFETY FIRST
Please be aware of construction activities and drive carefully through the work zone, including open-trench excavation. Open trenches are fenced off at the end of each day.
CONSTRUCTION UPDATE
Week of February 7-11 Construction Activities
- Crews will continue installing sewer pipe and maintenance holes along McMullin Drive. This activity includes road closures and detours.
- Crews will continue excavating and installing sewer service lines towards existing pump stations that will be decommissioned along McMullin Drive. This activity includes partial road closures and detours.
- Crews will continue excavating for new stormwater dry wells, which will be installed in the right-of-way adjacent to 60945 Ridge Drive.
DETOURS IN EFFECT
- A portion of McMullin Drive may be closed for excavation and sewer installation activities. Please reference the detour map below for additional information.
- Flaggers will be present for the construction activities as needed.

An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic.
PROJECT COMMUNICATIONS
General Project Notes
- Access to all businesses located at the end of Romaine Village Way will be maintained.
- Emergency access will be maintained throughout construction.
QUESTIONS OR COMMENTS?
Project Website: https://www.bendoregon.gov/swsewerpipe
Project Contact: Jake Sherman, Senior Project Engineer – Phone: (541) 383-4882 | Email: jsherman@bendoregon.gov

Above: Sewer main installation in McMullin Drive

Above: Excavation for the new stormwater facility in Cinder Lane