Wilson Avenue Corridor Project Update – July 8, 2022
The Wilson Avenue & 9th Street roundabout is now open!
SAFETY FIRST
The project team created a video to help explain how to navigate Bend’s first-ever bicycle-protected roundabout.
The roundabout works the same as a single-lane roundabout but has a protected bike lane around the outside, between the sidewalk and vehicle lane. If you’re riding a bike, you’ll have the option to ride in the protected bike lane or the vehicle travel lane.
Link to video: https://youtu.be/sCa5VpenG5Y
CONSTRUCTION UPDATE
9th Street & Wilson Avenue
- Landscape and irrigation work will continue through mid-July.
Work along Wilson Avenue will progress eastward to build improvements between 9th Street and 15th Street. Eastbound traffic between 9th Street and 15th Street on Wilson will be detoured at the end of July or early August. Access at 15th Street and Wilson Avenue will be maintained through October.
Construction of the full project corridor is anticipated to be complete by the end of 2023.
An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic.
GENERAL PROJECT NOTES
- Access to all area businesses along the construction area will be maintained.
- Please do not enter the construction zone before, during, or after hours.
- Daytime work hours are in effect from 7:00 AM – 6:00 PM.
PROJECT COMMUNICATIONS
- EMS, buses, and many other delivery/service providers have been included on this distribution list.
- Please help us spread the word to your clients, customers, and delivery personnel regarding detouring and closures.
- Share the project website information (provided below), where others can also sign up for updates.
- Please contact the project team if you are not the correct contact for your organization or if others need to be included.
QUESTIONS OR COMMENTS?
Project Website: www.bendoregon.gov/wilson
24-Hour Construction Phone Line: (541) 322-9919
Project Contacts
- Sinclair Burr, PE – Project Manager – sburr@bendoregon.gov
- ShanRae Hawkins – Project Public Involvement Coordinator – shanrae@hellostingray.com
The Wilson Avenue Corridor Project is the first Transportation General Obligation (GO) Bond project approved by voters in 2020.