Admiral & King Jehu Sewer Project Update – May 16, 2022

TENTATIVE CONSTRUCTION ACTIVITIES (KING HEZEKIAH WAY & KING JEHU WAY)

  • In general, construction sequencing will begin on King Hezekiah Way, followed by King Jehu Way, and then on Admiral Way.
  • Locate markings are painted on the ground, indicating where underground utilities are located.
  • Survey staking is ongoing on King Jehu and Admiral Way; please do not move or remove any wooden survey stakes.
  • Minor tree trimming activities and clearing will occur as needed.
  • Pre-hammering and trench excavation are ongoing on King Jehu.
  • Sewer main and lateral installation is complete on King Hezekiah; Activities to prepare for road restoration are upcoming.
  • Franchise utilities are relocating their facilities as needed concurrent with sewer construction activities.
  • Traffic control measures remain in place.

PROJECT PHOTO

Below is a photo showing a lateral trench excavation. The lateral connects to the sewer main line and extends to the edge of the right-of-way.

A photo showing a lateral trench excavation. There are pipes exposed in the trench.

TRAFFIC CONTROL

Traffic control signs have been staged and are ongoing on King Hezekiah and King Jehu. The map below shows the closure area (solid red line) and detour (blue dashed line). Local access will be provided on King Jehu Way, Hezekiah Way, and King Solomon Court for homeowners living on those streets. Please proceed with caution when driving in the construction zone.

A map of the traffic control plan depicting the road closure on King Hezekiah & King Jehu, and the detour route on King Hezekiah & King David.

Road Closed to Thru Traffic / Local Access Only

Local traffic (meaning homeowners who live adjacent to the construction zone) can drive past this sign to access their driveways/homes. Please use extreme caution when driving in the construction zone.

A photo a barricade, cones, and road signs marking the road closure to thru traffic and local access only.

RESOURCES

PROJECT CONTACT

Alex Doza, P.E., Assoc. DBIA | City of Bend, Project Engineer – adoza@bendoregon.gov or 541-678-2597

View All News