Columbia Roundabout Improvements Project Update – March 24, 2021
The Colorado Ave./Columbia St. Intersection Is Closed
SAFETY FIRST, THIS IS A WORK ZONE
More construction equipment has been moved into the area and activities begin to increase in the legs of the closed construction zone. Motorists – it is extremely important to obey the road closure signs. Pedestrians and bicyclists – as previously noted, circulation and closures continue to shift as construction progresses, so continue to be aware of your surroundings.
CONSTRUCTION PHOTOS
Above: Photo of new sidewalks on the NE corner of Colorado Ave. and Columbia St. The limits of the roundabout are already taking shape

Above: Photo of asphalt removal on the west leg of the Colorado Ave. and Columbia St. intersection
CONSTRUCTION UPDATE
March 24 through 30 – Colorado Ave./Columbia St. Intersection
- The first of new sidewalks have been poured. (see photo #1 below)
- Asphalt removal in the main intersection has begun. (see photo #2 below)
- The Colorado Avenue/Columbia Street intersection is closed. The closure is anticipated to last through the middle of May, 2021.
- The following detour remains in effect.

PROJECT DESIGN
- Below is a schematic of the proposed design for the Colorado/Columbia roundabout.

BUSINESS ACCESS
Business Access remains open on all legs of this project affected by the current detour.
Access to Mill Point, OSU-Cascades, 705-775 SE Bonnett Way, 600-650 SW Columbia, and Deschutes Ridge businesses is available by driving past this sign and through the Columbia Street/Shevlin Hixon Intersection.
QUESTIONS OR COMMENTS?
Project Website: www.bendoregon.gov/columbia-roundabouts
Project Phone Line: (458) 256-6009
Project Contacts:
George Franklet, City of Bend Project Engineer – gfranklet@bendoregon.gov or (541) 693-2182
Deedee Fraley, City of Bend Project Engineer – dfraley@bendoregon.gov or (541) 385-6199
Ron Hand, Project Public Involvement Coordinator – rhand@dowl.com or (541) 385-4772