Drake Pump Station Weekly Update – November 05, 2020

Drake Pump Station Nears Completion

  • K & E Excavating construction crews will be working on upgrading the pump station.
    • Commissioning of the new pump station is underway.
    • Demolition of the old pump station is to commence next week.
    • Major mechanical and electrical testing of the project is commencing.
  • Asphalt paving has been completed.
  • All major project elements are scheduled to be completed by Friday, November 13th
  • Active Culture is open during construction.
  • Work hours are from 7:00 a.m. to 6:30 p.m. Monday -Friday
    • During work hours
      • NW Riverside will be intermittently closed to thru-traffic from NW McKay Avenue to NW McCann Avenue.
      • NW Congress will be intermittently closed to thru-traffic from NW McKay Avenue to NW St. Helens Place.
      • Detour routes and traffic control devices will be implemented for both road closures.
  • Construction is dependent on weather conditions and other factors.

A photo of work crews and equipment doing asphalt paving on Riverside Blvd.
Above: Asphalt paving Riverside Blvd

A photo of the new concrete valve vault lid being delivered on a flatbed delivery truck equiped with a crane.
Above: Delivery of the new concrete valve vault lid

A photo of the opened control cabinet that contains all the programming to operate the new pump station.
Above: Control cabinet that contains all the programming to operate the new pump station

A photo of work crews and a concrete mixer pouring concrete curb between Riverside Blvd. and Congress St.
Above: Pouring concrete curb between Riverside Blvd. and Congress Street

  • Please stay out of work zones and away from construction equipment. Excavated areas are considered unsafe for yourself, children, and pets.
  • Walk and bicycle in designated areas only. 
  • Access to the construction area is limited to construction workers.
  • Do not remove barriers or warning signs/warning tape or fencing. 

Visit www.bendoregon.gov/drake-pump-station for current project information.

Project Hotline: (541) 207-1491