Drake Pump Station Weekly Update – October 16, 2020
Paving Activities Will Continue Into Next Week
- Additional paving activities will be occurring next week, including a complete resurfacing of the Riverside and Congress intersection.
- K & E Excavating construction crews will be working on upgrading the pump station.
- ADA curb ramp work is near complete, and asphalt paving was completed at a couple of intersections.
- Major mechanical and electrical aspects of the project are commencing.
- Active Culture is open during construction.
- Work hours are from 7:00 a.m. to 6:30 p.m. Monday -Friday.
- During work hours:
- NW Riverside will be intermittently closed to thru-traffic from NW McKay Avenue to NW McCann Avenue.
- NW Congress will be intermittently closed to thru-traffic from NW McKay Avenue to NW St. Helens Place.
- Detour routes and traffic control devices will be implemented for both road closures.
- During work hours:
- Drake pump station upgrade is scheduled to be completed in November 2020.
- Construction is dependent on weather conditions and other factors.

Above: Sidewalk work along NW Riverside Blvd

Above: ADA curb ramp and sidewalk work near the intersection of NW Congress St & NW Riverside Blvd

Above: Excavating work crews and equipment working on upgrading the pump station
- Please stay out of work zones and away from construction equipment. Excavated areas are considered unsafe for yourself, children, and pets.
- Walk and bicycle in designated areas only.
- Access to the construction area is limited to construction workers.
- Do not remove barriers or warning signs/warning tape or fencing.
Visit www.bendoregon.gov/drake-pump-station for current project information.
Project Hotline: (541) 207-1491
View All News