Empire Corridor Improvements Project Update – August 26, 2021

Thank you for your interest in the Empire Corridor Improvements Project.

Early morning work may occur through early September. Work will begin as early as 4:00 AM during this timeframe. This work is limited to the NE Butler Market Road and NE Purcell Blvd intersection.

Intermittent work will occur at the intersections of NE Wild Rivers Loop, NE Cradle Mountain Way, NE Purser Avenue, and NE Castle Avenue for the next few weeks.

  • One intersection will be closed at a time during work hours. All intersections will be open at the end of the workday.
  • Construction is dependent on weather, COVID-19 protocols, and other factors.
  • Workers may be working Saturday, August 28.
  • NE Butler Market Road and NE Purcell Blvd roundabout is scheduled to open in October. 

A photo of NE Purcell Blvd and NE Butler Market Road facing south. There are cones, barricades, and a ROAD CLOSED street sign closing the street during construction of the roundabout.
Above: 1 NE Purcell Blvd and NE Butler Market Road facing south.

Please Stay Out of Work Zone and Away From Construction Equipment 

  • The construction area is considered unsafe for yourself, children and pets.
  • Walk and bicycle in designated areas only.
  • Access to the construction area is limited to construction workers.
  • Do not remove barriers, warning signs, warning tape, or fencing.
  • Do not drive over construction cones or barriers.
  • Daytime work hours are in effect from 7:00 AM-5:30 PM. Closures are in effect at all times.

Please Use the Detour Route Around Construction Zones 

  • Detours are in place during construction.
  • There are many construction projects in the area and throughout the City of Bend. Travel safely.

A map exhibiting the NE Purcell Blvd. roadwork (May-July 2021), NE Butler Market Rd./NE Purcell Blvd. intersection closure and roundabout construction (May 3-September), and detour routes.

August-September 2021 Closure Notice to NE Purcell Blvd Area Residents 

Check in on our interactive, online map at www.bendoregon.gov/traffic.

Accommodation Information for People With Disabilities 

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic & CD formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at (541) 330-4018 or (541) 350-6012; Relay Users Dial 7-1-1, and (541) 385-6676.

Questions or Comments?

Visit www.bendoregon.gov/empire for current project information.  

24-Hour Construction Phone Line: (541) 200-6939

Project Contacts

Sinclair Burr, P.E., Project Manager – sburr@bendoregon.gov or (541) 330-4018

Linda Swearingen, Public Outreach Coordinator – lllswear@aol.com or (541) 350-6012