Ferguson Sewer Improvements Project Update – July 24, 2023

TRAFFIC CONTOL UPDATE

 

Traffic control is expected to shift to the fourth and final stage tomorrow, July 25, 2023. Ferguson Road will be closed eastbound from east of Sarah Drive to 27th Street. Local access to Mt. Vista Drive and Ferguson Court will be maintained from the westbound direction (see figure below).

Although this is the final stage of traffic closure for sewer installation, please be aware that there will be additional short-duration closures for road paving before the project is completed. More information will follow as it approaches.

STAGE 4 TRAFFIC CLOSURE

A satellite map showing the Ferguson Rd. closure for eastbound traffic from east of Sarah Drive to 27th Street.

RESOURCES

Project website: www.bendoregon.gov/fergusonsewer

Project Contact:

Alex Doza, PE, DBIA – City of Bend Project Engineer – adoza@bendoregon.gov or 541-323-8595