Murphy Corridor Improvements Project Update – June 24, 2021

Thank you for your interest in the Murphy Corridor Improvements Project.

Construction Activities – Week of June 28

  • Crews will continue backfill work on the BNSF Railway bridge abutment for the future Murphy Road extension connecting Brosterhous Road to 15th Street.
  • Work will continue on the Mechanically Stabilized Earth (MSE) retaining walls along the future extension.
  • Continued installation of storm drywells and manholes along Murphy Road.
  • Landscape and irrigation work will continue along Murphy Road.

An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic.

Contact the project team with concerns, comments, and questions at (541) 322-9919.

Accommodation Information for People With Disabilities

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic & CD formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at MurphyProjectTeam@bendoregon.gov or (541) 322-9919; Relay Users Dial 7-1-1, and (541) 385-6676. 