Murphy Corridor Improvements Project Update – September 9, 2021

Thank you for your interest in the Murphy Corridor Improvements Project.

Construction Activities – Week of September 13

  • Crews will begin to pour islands and sidewalks south of the Brosterhous Road roundabout between The Pines neighborhood and Caldera Drive. Please be prepared for flaggers coordinating traffic control. 
  • Work will continue on the retaining walls between the extension of Brosterhous Road and the BNSF bridge overcrossing.
  • The water main will be installed east of the BNSF bridge overcrossing.
  • Concrete work will continue on the BNSF bridge abutments.

An interactive map of closures and detours can be found at www.bendoregon.gov/traffic.

Contact the project team with concerns, comments, and questions at (541) 322-9919.

Accommodation Information for People With Disabilities

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic & CD formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at MurphyProjectTeam@bendoregon.gov or (541) 322-9919; Relay Users Dial 7-1-1, and (541) 385-6676.