Newport Corridor Improvements Project Update – April 21, 2023
SAFETY FIRST
The concrete that is being poured over the coming weeks has a specific cure time to provide an optimal life expectancy. Pedestrians should follow all designated routes around the newly formed curbs and sidewalks. The exterior of the concrete may appear dry but could still be curing beneath the surface.
CONSTRUCTION UPDATE FOR APRIL 20 – APRIL 27
Newport Corridor Improvements Scheduled Construction – Segment 4 (Knoxville Boulevard through the 14th Street Roundabout)
- Concrete Work
- Curing of the concrete roundabout truck apron continues.
- Forming and pouring of driveway aprons begins.
- Preparation and forming of sidewalks begin.
- Concrete is poured for the sidewalks.
DETOURS IN EFFECT- SEE DETOUR MAP BELOW
Traffic Closures and Changes
- NW Newport Avenue closed from Knoxville Boulevard through the 14th Street roundabout
- NW 14th Street closed between NW Ogden Avenue and NW Milwaukee Avenue (no alley outlets onto 14th Street)
- NW 15th Street closed between NW Milwaukee and NW Newport Avenue
- NW Milwaukee Avenue, one-way eastbound traffic only from NW Stannium Road to NW 12th Street
GENERAL PROJECT NOTES
- Access to all area businesses along the construction corridor will be maintained.
- Please do not enter the construction zone before, during, or after hours.
- Daytime work hours are in effect from 7:00 AM – 6:30 PM.
- The ‘Tree Preservation and Removal Overview Exhibits’ can be found on the project website. These exhibits provide design details about each tree being removed and where new trees will be planted.
- There are many construction projects in the area and throughout the City of Bend. Travel safely.
PROJECT COMMUNICATIONS
- EMS, buses, and other delivery/service providers have been included in the project updates distribution list.
- Please help us spread the word to your clients, customers, and delivery personnel regarding detouring and closures.
- Share the project website (provided below), where others can also sign up for project updates.
- Please contact the project team if you are not the correct contact for your organization or if others need to be included.
QUESTIONS OR COMMENTS?
Project Website: https://www.bendoregon.gov/newportimprovements
24-Hour Construction Phone Line: 541-200-6972
Project Contacts:
- Brittany Barker, PE – City of Bend Principal Engineer – bbarker@bendoregon.gov
- Peter Guth, Project Public Involvement Coordinator – pguth@dowl.com or 548-256-6007