Newport Corridor Improvements Project Update – August 6, 2021

SAFETY FIRST

We are still hearing from residents that motor vehicles are traveling at excessive speeds through local neighborhoods. Kids are still out of school, work at home is still commonplace, and these streets can be narrow. Please continue to allow more time to reach your destination, observe speed limits and follow detours.

Crews are working hard to finish the paving on Nashville Ave, but the asphalt is laid at temperatures in excess of 150° F. Like concrete, it requires time to set properly for optimal lifespan and quality. Please avoid using any freshly paved surfaces until traffic control devices are removed.

On Saturday, August 7, the concrete contractor will be working typical workday hours.

CONSTRUCTION INFORMATION KIOSK

The City’s informational kiosk will be open in front of Newport Market on Tuesday, August 10, from 12:00 PM-1:30 PM. You are welcome to stop by and meet with our team to answer any questions regarding this project.

CONSTRUCTION UPDATE

Segment 1

  • Nashville Ave. is in its homestretch; new sidewalks and ADA ramps will be formed and poured over the upcoming weeks, and asphalt is being laid this week.
  • The 9th St. & Newport Ave. roundabout is scheduled to be paved at the end of August and is scheduled to open in early September.

A photo of paving crews laying down the first layer of pavement at Federal St. and Nashville Ave.
Above: Paving crews laying down the first layer of pavement at Federal St and Nashville Ave.

A photo of the first layer of pavement laid at Harmon Blvd. and Nashville Ave.
Above: First layer of pavement is laid at Harmon Blvd and Nashville Ave.

Nashville/Newport Corridor Improvements Scheduled Construction – Segment 1

Week of August 5–August 12

  • Sidewalks and ADA ramps along Nashville Ave continue to be formed.
  • Landscaping continues along Nashville Ave.
  • Crews will begin forming for the concrete crosswalks at Harmon Blvd and Nashville Ave.
  • Stormwater planters along the 9th Street roundabout continue to be built.

Newport Corridor Improvements Scheduled Construction – Segment 5 (Juniper St. to College Way) 

Week of August 5–August 12

  • Cascade Natural Gas will continue relocating their new gas main.

DETOURS IN EFFECT

Traffic Closures and Changes

  • Nashville Ave. from Newport Ave. to Pageant Park is closed.
  • Newport Ave. from NW 7th St. to NW 10th St. is closed.
  • The intersection at NW Juniper St and Newport Ave. will be closed.
  • The intersection at NW Knoxville Blvd and Newport Ave. will be closed.
  • One-way local access only on Newport Ave from NW Juniper St. to College Way.

A map of Segments 1 & 5 depicting road closures, local access only, westbound local access only, eastbound detour, and westbound detour from August 2 to early-September 2021.

All businesses along Newport Ave. will be open through construction. Business access signs will be placed on the following routes:

  • NW Portland Ave.
  • NW 14th St.
  • NW Newport Ave.

GENERAL PROJECT NOTES

  • Access to all area businesses along the construction corridor will be maintained. New ‘business open’ signage continues to be installed.
  • Businesses between 9th St. and 11th St. can be accessed using the rear alley and rear parking areas.
  • Please do not enter the construction zone before, during, or after hours.
  • Daytime work hours are in effect from 7:00 AM–6:30 PM
  • The ‘Tree Preservation and Removal Overview Exhibits’ can be found on the project website. These exhibits provide design details about each tree being removed and where new trees will be planted.
  • There are many construction projects in the area and throughout the City of Bend. Travel safely.

PROJECT COMMUNICATIONS

  • EMS, buses, and other delivery/service providers have been included in the project updates distribution list.
  • Please help us in spreading the word to your clients, customers, and delivery personnel regarding detouring and closures.
  • Share the project website (provided below), where others can also sign up for updates using the ‘PROJECT UPDATES’ button.
  • Please contact the project team if you are not the correct contact for your organization or if others need to be included.

QUESTIONS OR COMMENTS?

Project Website: https://www.bendoregon.gov/newportimprovements

24 Hour Construction Phone Line: (541) 200-6972.

Project Contacts: 

Drew Wells, City of Bend Project Engineer – awells@bendoregon.gov or (541) 588-0581

Peter Guth, Project Public Involvement Coordinator – pguth@dowl.com or (548) 256-6007