Newport Corridor Improvements Project Update – March 31, 2023
SAFETY FIRST
When you see orange signs and devices, be aware that you are nearing a work zone where workers may be present. You should slow down and watch for workers working near or on the road. This will help you avoid accidents and keep everyone safe. Remember that work zone crashes are serious for workers and drivers alike, so it’s important to be responsible and careful in work zones.
CONSTRUCTION UPDATE FOR MARCH 30 – APRIL 06
Newport Corridor Improvements Scheduled Construction – Segment 4 (Knoxville Boulevard through the 14th Street Roundabout)
- Construction of the stormwater planters continues.
- Forming of the walls for the stormwater planters on Newport Avenue continues.
- Excavation for stormwater planters along Newport Avenue continues.
- Replacement of domestic water service lines continues.
- Begin the replacement of the northeast sidewalk at the Juniper and Newport intersection.
- Continue the construction of the subgrade and aggregate base.
- Begin prepping the subgrade for concrete curbing.
DETOURS IN EFFECT – SEE DETOUR MAP BELOW
Traffic Closures and Changes
- NW Newport Avenue closed from Knoxville Boulevard through the 14th Street roundabout
- NW 14th Street closed between NW Ogden Avenue and NW Milwaukee Avenue (no alley outlets onto 14th Street)
- NW 15th Street closed between NW Milwaukee and NW Newport Avenue
- NW Milwaukee Avenue, one-way eastbound traffic only from NW Stannium Road to NW 12th Street

GENERAL PROJECT NOTES
- Access to all area businesses along the construction corridor will be maintained.
- Please do not enter the construction zone before, during, or after hours.
- Daytime work hours are in effect from 7:00 AM – 6:30 PM.
- The ‘Tree Preservation and Removal Overview Exhibits’ can be found on the project website. These exhibits provide design details about each tree being removed and where new trees will be planted.
- There are many construction projects in the area and throughout the City of Bend. Travel safely.
PROJECT COMMUNICATIONS
- EMS, buses, and other delivery/service providers have been included in the project updates distribution list.
- Please help us spread the word to your clients, customers, and delivery personnel regarding detouring and closures.
- Share the project website (provided below), where others can also sign up for project updates.
- Please contact the project team if you are not the correct contact for your organization or if others need to be included.
QUESTIONS OR COMMENTS?
Project Website: https://www.bendoregon.gov/newportimprovements
24-Hour Construction Phone Line: 541-200-6972
Project Contacts:
- Brittany Barker, PE – City of Bend Principal Engineer – bbarker@bendoregon.gov
- Peter Guth, Project Public Involvement Coordinator – pguth@dowl.com or 548-256-6007