North Interceptor Sewer Line Project Update – September 30 , 2020

Thank you for your interest in the North Interceptor Sewer Line Project. The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations and increase sewer capacity as part of the Community-supported Growth Plan.

The project is broken up into three distinct Phases:

  • Phase I: Summer 2019 – December 2020, begins at the City’s Water Reclamation Facility and extends to Pioneer Loop. 
  • Phase II: June 2020 – Spring 2022, Pioneer Loop through Juniper Ridge to Clausen Road just west of Highway 97.
  • Phase III: TBD, Clausen Road to O.B. Riley Road.

A map depicting phases 1 through 3, the future East Interceptor, the Urban Growth Boundary, and Bend's city limits.
Above: North Interceptor Alignment

Construction is progressing in Phase I and is on schedule to be complete by December 2020. The remaining work is predominately on City property at the Water Reclamation Facility. Revegetation of private property along Gentry Loop will take place this fall.

Construction is currently ongoing in Phase II – Segment 1 (Pioneer Loop and Margaret Lane). Pioneer Loop is open to residents; however, final roadwork restoration will take place later this fall and may require intermittent closures. As crews continue working west on Margaret Lane and approach Deschutes Market Road, please be prepared for 2-3-minute delays on Deschutes Market Road due to trench blasting through the week of October 5th. Blasting activities are scheduled for Tuesdays and Thursdays in the afternoon. Flaggers will be in place to direct traffic during this period safely.

Construction is also ongoing in Phase II – Segment 2 (City-owned Juniper Ridge Property). Crews continue to clear the work zone and blast for future pipe installation. This area remains closed to all unauthorized personnel until completion of construction.

A map depicting the Juniper Ridge Construction Zone, the COID Pilot Butte main canal, and Phase II Segment 2 sewer alignement - Juniper Ridge area.
Above: Phase II Segment 2 Sewer Alignment

Construction of Phase II – Segment 3 (BNSF railroad, adjacent to and across HWY 97 to Clausen Road), will begin in late October. This phase of the project includes construction along Highway 97. Lane restrictions may be in effect during this time for the safety of both the traveling public and the construction workers. Nightwork will be required along Highway 97 from 7 p.m. to 6 a.m. Access to private properties and businesses will be maintained at all times.

A map depicting Phase II Segment 3 - Clausen Rd to Juniper Ridge.
Above: Phase II Segment 3 Sewer Alignment 1

For more detailed project information and interactive maps, please visit our project Open House (details below). Thank you for your patience and support as we complete this important infrastructure project.

Open House Information – Ongoing

In light of restrictions on public gatherings, the City of Bend invites you to attend a virtual open house. The virtual open house is a platform for you to interact remotely with the City and its contractors. It features virtual exhibits and provides the opportunity to:

  • See the alignment in greater detail
  • Learn about traffic control impacts
  • Get answers to your questions
  • Learn more about what to expect during construction
  • Offer comments and feedback

To attend the virtual open house, obtain additional project information, or sign up for project update notifications, please visit the project website at www.bendoregon.gov/north-interceptor. Additionally, you may call the project team at (541) 382-3264.

Photos From Phase II Construction

An aerial photo of blasting taking place along Margaret Lane.
Above: Blasting along Margaret Lane

An aerial photo overlooking work crews and equipment worknig at the Pioneer Loop Crossing.
Above: Pioneer Loop Crossing

A photo of work crews and equipment working on the Pioneer Loop Restoration.
Above: Pioneer Loop Restoration

A photo of Pioneer Loop with equipment and a mound of earth behind cones, barricades, and a fenced off parameter.
Above: Pioneer Loop

A photo of Pioneer Loop with a mounds of earth and equipment behind cones and a fenced off parameter.
Above: Pioneer Loop

Accommodation Information for People With Disabilities

These meetings/event locations are accessible. Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic formats, and CD Formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at northinterceptorinfo@bendoregon.gov or (541) 382-3264; Relay Users Dial 7-1-1, and (541) 385-6676. Providing at least three days’ notice prior to an event will help ensure availability.

View All News