Project Kickoff and February Update

Project Benefits:

  • MOBILITY: Intersection improvements and the addition of a railway overcrossing to reduce delays and significantly improve emergency medical services and fire response times for citizens
  • CONNECTIVITY: Improved traffic connectivity to adjoining streets, parks and schools
  • SAFETY: Improved visibility at intersections and designated crossings, reduced vehicle conflict

 

Current Activities:

  • The selected Design-Builder received notice to proceed for the alternatives analysis phase in January 2019
  • Survey and geotechnical work are underway along Murphy, between Parrell and 15th.
  • The project team is reviewing previous design efforts and evaluating improvement options available (Alternatives Analysis).

 

Upcoming Activities:

  • Spring 2019: Open house to discuss existing conditions, project goals, and solicit community input
  • Early Summer 2019: Open house at conclusion of alternatives analysis
  • Late Summer 2019: Present design and discuss upcoming construction
  • Fall 2019: Construction Begins