Wilson Avenue Corridor Project Update – April 12, 2024

CONSTRUCTION UPDATE: April 15 – April 19

 

STAGE 2 Improvements: Second Street to Fourth Street

 

  • Crews will prepare the subgrade and lay aggregate for paving on Wilson Avenue, east of Third Street.
  • Excavation work will continue along Wilson Avenue, between Second and Third streets.
  • Utilities relocation work will continue.
  • Crews will test the new waterline on Wilson Avenue, east of Third Street.
  • Stormwater installation work will continue between Fourth and Fifth Street on Wilson Avenue.
  • Signal poles and mast arms are planned to be installed at the intersection.  This will not result in any immediate traffic control changes. 

TRAFFIC CHANGE IN EFFECT:

Traffic light at Third Street and Wilson Avenue converted to a temporary stop sign during construction

The traffic signal at Third Street and Wilson Avenue has been temporarily replaced with a stop sign as part of the Wilson Avenue Corridor Project. For those traveling eastbound on Wilson Avenue at the Third Street intersection, the only option will be a right turn to go southbound on Third Street; there will be no left turn option to go northbound on Third Street. The removal of the signal places construction a month ahead of schedule, with completion expected in May.  

The new traffic signal will enhance traffic flows and improve both driver and pedestrian safety. 

Detour Map

beginning Feb 8, no left turns at Third and Wilson. Full closure on Wilson between 3rd st and 4th st.

The Wilson Avenue Corridor is a multi-phase modernization project that will improve safety and east-west connectivity for all users along Wilson Avenue from Second Street to 15th Street. 

Waterline system upgrades are being constructed as part of the project to optimize synergy opportunities. 

Wilson Project construction stages

 


GENERAL PROJECT NOTES 

  • Access to all area businesses along the construction area will be maintained.
  • Please do not enter the construction zone before, during, or after hours.
  • Daytime work hours are in effect from 7 a.m. – 6 p.m. 
  • There are many construction projects in the area and throughout the City of Bend. Travel safely.

PROJECT COMMUNICATIONS

  • EMS, buses and other delivery/service providers have been included on this distribution list.
  • Share the website information where others can also sign up for updates at bendoregon.gov/wilson

QUESTIONS OR COMMENTS?

  • Construction Phone Line: (541) 322-9919
  • Project website: bendoregon.gov/wilson
  • Project Contacts:
    • Sinclair Burr – PE, Project Manager
    • ShanRae Hawkins – Project Public Involvement Coordinator

The Wilson Avenue Corridor Project is the first Transportation General Obligation (GO) Bond project approved by voters in 2020. To learn about more projects around Bend included in the GO Bond, visit bendoregon.gov/gobond.