Wilson Avenue Corridor Project Update – June 02, 2023
CONSTRUCTION UPDATE: Week of June 5 – June 9
Modernization work on Wilson Avenue from 4th Street through Centennial Street is scheduled through the fall. Please be prepared for flaggers and a westbound detour between 4th and 9th Street.
STAGE ONE: 4th Street through Centennial Street, including Edgewater Lane
Starting Wednesday, June 7, crews will be working on the installation of the new waterline along Edgewater Lane. Please avoid parking on the eastside of Edgewater Lane. Waterline construction on Edgewater is expected to last approximately two weeks. Future parking restriction instructions will be provided for paving activities on Edgewater Lane.
WILSON AVENUE WESTBOUND DETOUR – beginning the week of May 15
Take 9th Street south to Reed Market Road. Turn right on Reed Market Road. Turn right on 3rd Street and continue to Wilson Avenue.
Stage 1: May 15, 2023 – Fall 2023
Modernization of 4th Street through Centennial Street Improvements include:
- Crossing at 5th Street with refuge island to help protect pedestrians
- Dura-curbs used for on-street bike lane protection
- Curb extensions to improve the visibility of pedestrians along Wilson Avenue
- Crosswalk lighting will be added at the 2nd Street and 5th Street pedestrian crossings
GENERAL PROJECT NOTES
- Access to all area businesses along the construction area will be maintained.
- Please do not enter the construction zone before, during, or after hours.
- Daytime work hours are in effect from 7:00 AM – 6:00 PM.
- There are many construction projects in the area and throughout the City of Bend. Travel safely.
PROJECT COMMUNICATIONS
- EMS, buses, and other delivery/service providers have been included on this distribution list.
- Share the website information where others can also sign up for updates. www.bendoregon.gov/wilson
- Please contact the project team if you are not the correct contact for your organization or if others need to be included.
QUESTIONS OR COMMENTS?
Construction Phone Line: (541) 322-9919
Project website: www.bendoregon.gov/wilson
Project Contacts:
- Sinclair Burr, PE – Project Manager
- ShanRae Hawkins – Project Public Involvement Coordinator
The Wilson Avenue Corridor Project is the first Transportation General Obligation (GO) Bond project approved by voters in 2020. To learn about more projects around Bend included in the GO Bond, visit www.bendoregon.gov/gobond.