Wilson Avenue Corridor Project Update – September 23, 2022
SAFETY FIRST
Please stay aware of your surroundings as construction equipment is continuously moving. Motorists should follow the designated detour signs, avoiding use of private driveways and parking lots in attempts to bypass the construction.
CONSTRUCTION UPDATE – Modernization of 9th Street to 15th Street
September 26 through September 30
- Crews will continue prepping for paving, scheduled for October 6 and 7.
- Street excavation and curb work are ongoing.
- Installation work will begin on the irrigation system.
Upcoming Traffic Impacts (October 6 and 7)
Access on Wilson Avenue will be impacted on October 6 and 7 for limited durations beginning at 7:00 AM (typically less than 20 minutes) to accommodate paving. Please be prepared for flaggers coordinating traffic control and up to 20-minute delays. EMS, garbage, mail, and other services will be maintained.
Westbound traffic will be maintained on Wilson Avenue through October.
Drivers will have full access, and no significant impacts are anticipated to 15th Street until early March 2023. Construction of the entire project corridor is anticipated to be completed by the end of 2023.
An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic.
GENERAL PROJECT NOTES
- Access to all area businesses along the construction area will be maintained.
- Please do not enter the construction zone before, during, or after hours.
- Daytime work hours are in effect from 7:00 AM – 6:00 PM.
- There are many construction projects in the area and throughout the City of Bend. Travel safely.
PROJECT COMMUNICATIONS
- Please help us in spreading the word to your clients, customers, and delivery personnel regarding detouring and closures.
- EMS, buses, and many other delivery/service providers have been included on this distribution list.
- Share the project website information (provided below), where others can also sign up for updates.
- Please contact the project team if you are not the correct contact for your organization or if others need to be included.
QUESTIONS OR COMMENTS?
Project Website: www.bendoregon.gov/wilson
Construction Phone Line: (541) 322-9919
Project Contacts
- Sinclair Burr, PE – Project Manager – sburr@bendoregon.gov
- ShanRae Hawkins – Project Public Involvement Coordinator – shanrae@hellostingray.com
The Wilson Avenue Corridor Project is the first Transportation General Obligation (GO) Bond project approved by voters in 2020.