27th Street Design Concepts

Budget

$4.815M was allocated from the 2020 Transportation GO Bond for both the North and South segments of 27th Street improvements between US Hwy 20 and Reed Market Road.


North Concepts (27th St from US HWY 20 to Bear Creek Rd)

Concept A: Buffered Bike Lanes (at Street Level)

Design details are listed below

  • Slight narrowing of vehicle lanes and center median to provide wider bicycle facilities.
  • No major changes to current sidewalks and landscape buffers.
  • Cost: $860,000

 

Concept B: Protected Bike Lanes (Raised at Sidewalk Level)

Design details are listed below

  • Slight narrowing of the center median and the travel lanes
  • Conversion of existing street level bike lanes to raised protected bike lanes.
  • No major changes to current sidewalks and landscape buffers.
  • Cost: $3.0 million 

North Concepts Considerations Matrix

table lists concept cost and other considerations also listed above for concepts listed above


South Concepts (27th St from Bear Creek Rd to Reed Market Rd)

Concept A: Shared Use Path (West Side) and Sidewalk Infill (East Side)

Design details are listed below

  • No roadway widening, generally retains existing roadway pavement width. Converts the west side sidewalk into a shared use path for people walking and bicycling.
  • Provides a continuous sidewalk on the east side by filling gaps.
  • Cost: $5.3 million 

 

Concept B: Sidewalk Infill (West Side) and Shared Use Path (East Side)

Design details are listed below

  • No roadway widening, generally retains existing roadway pavement width. Converts the east side sidewalk into a shared use path for people walking and bicycling.
  • Provides a continuous sidewalk on the west side by filling gaps.
  • Cost: $5.0 million

South Concepts Considerations Matrix

table lists concept cost and other considerations also listed above for concepts listed above


27th Street Roll Plots