Columbia Roundabout Improvements Project Update – May 27, 2021
SAFETY FIRST
We hear from businesses in the area that motor vehicles are traveling at excessive speeds through local business parks. Please allow more time to reach your destination and follow detours.
With the upcoming concrete pour and changes in pedestrian paths, please follow the designated route on site. Concrete has a specific curing time; please do not use new sidewalks until crews have established the new pedestrian paths.
CONSTRUCTION UPDATE
![]() |
![]() |
Above: Sidewalks are ready for forming and the new concrete to be poured

Above: Equipment is arriving for asphalt removal
Simpson Avenue/Columbia Street Scheduled Construction
Week of May 27–June 2 (No work on May 31 in observance of Memorial Day)
- Framing and pouring the northwest and southeast sidewalks.
- Pedestrian paths are realigned to the new sidewalks
- Clearing and preparation for the northeast and southwest sidewalks
- Removal of existing asphalt begins
DETOURS IN EFFECT
Current Road Closures
- Simpson Ave and Columbia Intersection

GENERAL PROJECT NOTES
- Business Access will remain open on all legs of this project affected by the detour.
- Please do not enter the construction zone before, during, or after hours.
- There are multiple construction projects in the area and throughout the City of Bend. Travel safely.
QUESTIONS OR COMMENTS?
Project Website: www.bendoregon.gov/columbia-roundabouts
Project Phone Line: (458) 256-6009
Project Contacts
Deedee Fraley, City of Bend Senior Project Engineer – dfraley@bendoregon.gov or (541) 385-6199
Peter Guth, Project Public Involvement Team – pguth@dowl.com or (541) 385-4772
Ron Hand, Project Public Involvement Team – rhand@dowl.com or (541) 385-4772