Wilson Avenue Corridor Project Update – June 4, 2022

SAFETY FIRST

Roundabout Safety Tips: 

  • Slow down as you approach the roundabout and be prepared to yield to pedestrians and vehicles already in the traffic circle. 
  • Use your turn signals to tell other drivers where you are going.  
  • Stop only if there is no opening for you to safely enter the circle. 
  • In the case of a multi-lane roundabout, follow posted signs to make sure you’re in the correct lane for where you want to go. 

CONSTRUCTION UPDATE FOR JUNE 6 – JUNE 11

Wilson Avenue Corridor Project – 9th Street & Wilson Avenue Roundabout

  • Crews will concrete pave the new roundabout. 
  • Landscape and irrigation work will begin, including placing rock and boulders.
  • Sidewalk prep work will continue. 
  • Crews will be working Saturday, June 11.

An aerial photo of the 9th Street & Wilson Ave. roundabout as of 6/2/2022.
Above: 9th Street and Wilson Avenue 6/2/22

A image of the 9th Street & Wilson Avenue roundabout, looking east as of 6/2/2022
Above: 9th Street and Wilson Avenue Roundabout – looking east 6/2/22

DETOURS IN EFFECT

The 9th Street/Wilson Avenue Intersection Remains Closed.  

An interactive map of closures and detours can be found at www.bendoregon.gov/traffic. 

 

The construction of the 9th Street and Wilson Avenue Roundabout is anticipated to be completed by the end of June 2022. 

GENERAL PROJECT NOTES

  • Access to all area businesses along the construction area will be maintained.
  • Please do not enter the construction zone before, during, or after hours.
  • Daytime work hours are in effect from 7:00 AM – 6:00 PM.

PROJECT COMMUNICATIONS

  • EMS, buses, and many other delivery/service providers have been included on this distribution list.
  • Please help us spread the word to your clients, customers, and delivery personnel regarding detouring and closures.
  • Share the project website information (provided below), where others can also sign up for updates.
  • Please contact the project team if you are not the correct contact for your organization or if others need to be included.

QUESTIONS OR COMMENTS?

Project Websitewww.bendoregon.gov/wilson

24-Hour Construction Phone Line: (541) 322-9919

Project Contacts

The Wilson Avenue Corridor Project is the first Transportation General Obligation (GO) Bond project approved by voters in 2020. 

To learn about more projects around Bend included in the GO Bond, visit www.bendoregon.gov/gobond