Columbia Roundabout Improvements Project Update – June 23, 2021

SAFETY FIRST

Cascade East Transit is operating its Ride the River shuttle out of Park & Float near The Pavilion. There will be an increase in pedestrian traffic along Shevlin Hixon Dr. Please use additional caution when driving the detour routes as the hot weather continues.

CONSTRUCTION UPDATE

An aerial photo overlooking the new sidewalks open for pedestrian use.
Above: Installation of utilities under the new sidewalk on the southwest side of the roundabout

An aerial photo overlooking work crews and equipment grading the southwest corner of Simpson and Columbia for the new sidewalk.
Above: Preparations for the subgrade using large bucket tractors to move dirt and arrogate to establish new grades

SIMPSON AVENUE/COLUMBIA STREET SCHEDULED CONSTRUCTION

Week of June 23–June 30

  • Conduit and utilities will continue to be installed.
  • New stormwater structures and pipes continue to be installed.
  • Crews will begin laying the subgrade that establishes the grading of the roadway below the asphalt.

DETOURS IN EFFECT

Current Road Closures 

  • Simpson Ave and Columbia Intersection

A map depicting the work area and road closure at the Simpson Ave. & Columbia St. intersection, and the detour along Century Dr., Colorado Ave., and Shelvin Hixon Dr.

GENERAL PROJECT NOTES

  • Business access will remain open on all legs of this project affected by the detour.
  • Please do not enter the construction zone before, during, or after hours.
  • There are multiple construction projects in the area and throughout the City of Bend. Travel safely. 

QUESTIONS OR COMMENTS? 

Project Website: www.bendoregon.gov/columbia-roundabouts 

24-Hour Construction Phone Line: (458) 256-6009

Project Contacts

Deedee Fraley, City of Bend Senior Project Engineer – dfraley@bendoregon.gov or (541) 385-6199

Peter Guth, Project Public Involvement Team – pguth@dowl.com or (541) 385-4772