North Interceptor Sewer Project Update – May 4, 2020
Thank you for your interest in the North Interceptor Sewer Line Project.
The North Interceptor Sewer Line is a large diameter sewer transmission line that allows the City to decommission pump stations and increase sewer capacity as part of the community-supported Growth Plan.
The North Interceptor Sewer Line Project is divided into three distinct phases:
Phase I: Summer 2019 – Fall 2020; Begins at the City’s Water Reclamation Facility and extends to Pioneer Loop
Phase II: June 2020 – Winter 2022; Pioneer Loop through Juniper Ridge to Clausen Road, west of Highway 97
Phase III: To be Determined; Clausen Road to O.B. Riley Road
Upcoming Phase I Activities
- Complete electrical conduit installation for the pump station and electrical building
- Installation of electrical building equipment and rough-in
- Installation of equipment pads for pump discharge
- Begin installation of pumps and discharge pipeline
- Install diversion manholes west of the North Unit Main Canal
Upcoming Phase II Activities
- The Guaranteed Maximum Price (GMP) for Phase II construction is scheduled to be presented to City Council on May 6, 2020.
- Design is progressing to 100%.
- The City will be sending information regarding construction, as well as open house information.

Above: Filling electrical conduit trenches with dyed concrete
If you have questions or concerns, please call the project team at 541-382-3264 or visit our project website at www.bendoregon.gov/north-interceptor.
Accommodation Information for People with Disabilities
Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic formats, and CD Formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at northinterceptorinfo@bendoregon.gov or 541-382-3264; Relay Users Dial 7-1-1, and 541-385-6676.