SW Sewer Basin Phase 2B Project Update – April 18, 2022

SAFETY FIRST

Please be aware of construction activities and drive carefully through the work zone, including open-trench excavation. Open trenches are fenced off at the end of each day.

CONSTRUCTION UPDATE 

Week of April 18 construction activities:

  • Crews will continue excavating and installing the new sewer main along Mahogany Street. This construction includes full closures and detours (reference image below for detour).
  • Crews will continue removing the existing curb and asphalt along McMullin Drive. This construction includes partial closures and detours.

DETOURS IN EFFECT 

  • A portion of the streets mentioned above may be closed for grading and sewer construction activities. Please follow the necessary road closed and detour signs and reference the detour map below for additional information.
  • Flaggers will be present for the construction activities as needed.

A detour map depicting the work zone/road closure on Mahogany St (between Granite Dr. & McMullin Dr.) and the detour on Kings Ln., Driftwood Ln., McMullin Dr., Cinder Ln., Alpine Dr., Arrow Wood Dr., and Aspen Dr.

An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic 

PROJECT COMMUNICATIONS

General Project Notes

  • Access to all businesses located at the end of Romaine Village Way will be maintained.
  • Emergency access will be maintained throughout construction.

 QUESTIONS OR COMMENTS?

A photo of work crews using an excavator to remove the existing maintenance hole at the Mahogany/Granite intersection.
Above: Removal of the existing maintenance hole at the Mahogany/Granite intersection

A photo of the removal of existing roadway along McMullin Drive. There are cones and caution tape surrounding an excavated trench along the right side of the roadway. There is a truck and excavator on the roadway.
Above: Removal of the existing roadway along McMullin Drive