Resurfacing on Reed Market Road will Impact Traffic
Reed Market Road (Bond Street to Bend Parkway) is scheduled for asphalt overlay Monday, September 24, 2012. Low nighttime temperatures require the paving work to be completed during warmer, daytime hours. Road closures will be required to complete the work. Flaggers and local traffic detours will be in place. Please choose alternate routes to avoid the construction area.
Construction Schedule
The general contractor on this project is High Desert Aggregate. Project dates are estimates based on favorable conditions; schedule variances may occur due to weather or other unforeseen circumstances.
- 9/24 Reed Market Rd. CLOSED, Bond St. to Bend Parkway (Southbound on and off ramps will be closed)
What to Expect During Construction
- Construction hours will begin at 8:00 a.m. – 8:00 p.m. (weather permitting)
- Road closures – detours and traffic delays
- Signage for Local Access will be posted on roadway
- Parking, load, and moisture restrictions
- Construction noise and dust
- Use alternate routes to avoid construction zones