Awbrey Butte Waterline Improvement Project Update – January 19, 2024

The Awbrey Butte Waterline Improvement Project will improve Bend’s ability to deliver water across the City and increase the system’s resiliency and reliability by installing approximately 4.25 miles of pipeline. 

PROJECT UPDATE

PHASE 1

Subproject 4 (Awbrey Reservoir Outlet Transmission Upsize) and Subproject 5 (NW Ninth Street waterline) improvements will continue through March. Impacts to NW Ninth Street are as follows:

  • Periodic closures for NW Ninth Street between NW Trenton and Roanoke Avenue for temporary surface restoration, and construction of stormwater improvements.
  • After crews have left NW Ninth Street for the winter, they will return in the spring for permanent paving restoration between NW Trenton and Newport Avenue.

PHASE 2

Phase 2 waterline and sewer main construction work will begin January 22* in Shevlin Park Road. Construction in Portland Avenue between Wall Street and Steidl Road began on January 16. The schedule is weather-dependent. View additional details below. 

Work will take place within the Public Right of Way and includes trenched construction with rock excavation, pipe, fittings, valves, water meters, and surface restoration.  

In advance of construction activities in your neighborhood, residents will receive a more detailed notification with specific information regarding construction impacts.  

SUBPROJECT 8

Stage 1: Shevlin Park Road – Single Lane Closure with Detour begins January 22* 

Phase 2 waterline and sewer main construction work will begin January 22* in Shevlin Park Road. The work was rescheduled due to inclement winter weather conditions.

Water and sewer main construction will require a single-lane closure of Shevlin Park Road. The direction of detoured traffic will switch as construction progresses. Expect periodic closures for northbound travel through the Mount Washington and Shevlin Park Road Roundabout when entering from the south. See the detour map below. 

Upcoming Work 

Tree removal will take place beginning the week of January 29 along the southern boundary of the COCC property to allow for the installation of the 30-inch waterline. 

 

Water and sewer main construction will require a single-lane closure of Shevlin Park Road.  The direction of detoured traffic will switch as construction progresses.

SUBPROJECT 2 

Portland Avenue and Bridge – Full Road and Bridge Closure with Detour in Effect 

Stage 1 construction began January 17 and requires a full closure of Portland Bridge for vehicular traffic, in effect through mid-March. Pedestrians and bicyclists walking their bikes can continue using the sidewalk on the north side of the bridge. See map below. 

A two-way vehicular detour route utilizes Awbrey Road, Newport Avenue and Wall Street. Parking will be restricted 24/7 along NW Awbrey Road between Portland Avenue and Newport Avenue on the East Side. This parking restriction is to improve safety along the detour route while the Portland Avenue Bridge is closed for waterline construction. See the detour map below. 

To alleviate congestion on Awbrey Road, we encourage eastbound traffic to utilize Newport Avenue at NW 9th or other available routes. This will help ease traffic flow and minimize delays during construction. 

Short durations for periodic asphalt and concrete restoration work are expected through Spring 2025. 

A portion of the Portland Avenue GO Bond Improvements (NW Ninth Street to the bridge) and select stormwater improvements are being constructed as part of Subproject 2 to optimize synergy opportunities
Portland Bridge closure begins mid january through march 2024. Detour includes Awbrey, Newport and Bond streets

Phase 2 improvements:

Awbrey Waterline project includes three phases with several subprojects per phase 

Selective stormwater improvements and a portion of the voter-approved 2020 Transportation GO Bond Portland Avenue improvements are being constructed as part of the Awbrey Butte Waterline Improvement Project to take advantage of synergy opportunities.  

What to Expect During Phase 2 Construction 

We’re committed to limiting construction impacts on neighbors and community members. Our construction management plan includes minimizing impacts from traffic, noise, dust, and other construction concerns. 

Construction will generally occur Monday to Friday from 7:00 a.m. to 5:00 p.m., with extended hours and weekends (as needed and on a very limited basis). Any work that includes crossing driveways will be coordinated with residents one day prior to commencing work and again on the day of work before being impacted. Emergency Medical Services, mail, garbage, and delivery services will have continued access.  

If there is a planned shutdown of the water service that will impact your property, you will be notified ahead of time. If there are delays to the schedule, a project representative will be on-site and will attempt to notify you. 

The construction is taking place within the Public Right-Of-Way. Please visit the project website to learn more about public Right-Of-Way.  


 
You can monitor current and upcoming detours and closures at bendoregon.gov/traffic

For additional information, Subproject details, or to sign up for regular project updates for the Awbrey Butte Waterline Improvement Project, please visit: bendoregon.gov/awbrey-waterline.  