Neff and Purcell Improvement Project Update – January 5, 2024
SAFETY FIRST
Purcell Boulevard from Holliday Avenue to Full Moon Drive remains fully closed to complete concrete pouring of sidewalk and driveways. Crews and equipment will be working within the roadway. Please use signed detour.
CONSTRUCTION UPDATE AND ACTIVITIES – January 8 – 12
North sidewalk infill on Neff Road (Eastwood Drive to Cliff Drive) is complete.
Neff and Purcell Intersection
- Installation of irrigation and landscaping continues, expect shoulder work and lane shifts.
- Some landscape plantings and restoration following construction may occur in the spring due to weather.
Purcell Extension – Opening late January (weather permitting)
- Roadway closures continue. Please follow signed detour routes.
- Sidewalk concrete work continues, expect shoulder work and flaggers.
Note: Dates are estimates and subject to change.
ROAD CLOSURES AND DETOURS
- Neff and Purcell Intersection expect single lane closure with flagging.
- The Purcell Extension closures and detours will continue through January, weather permitting. Please use signed detour routes.
Temporary Pedestrian Access Routes
Please use marked temporary pedestrian detours. These temporary pedestrian access routes will change as needed during different phases of work.
Interactive Traffic Impacts Map
You may also monitor other detours and closures at bendoregon.gov/traffic.
QUESTIONS AND COMMENTS?
- Project Phone Line: (458) 202-7348
- Project Email: neffpurcell@bendoregon.gov
- Project Website: bendoregon.gov/neff-purcell
- Project Engineer: Drew Wells, PE
This project is partly funded by the voter-approved 2020 Transportation General Obligation (GO) Bond. To learn about more projects around Bend included in the GO Bond, visit bendoregon.gov/gobond.