Wilson Avenue Corridor Project Update – July 29, 2022

SAFETY FIRST

The new detour is in effect through October. Please slow down and follow traffic control signs (See detour details below).

CONSTRUCTION UPDATE

Modernization of 9th Street to 15th Street – August 1 Through August 5

  • Crews will continue asphalt removal and street excavation work along Wilson Avenue between 9th Street and 15th Street.

Construction of the full project corridor is anticipated to be complete by the end of 2023.  

An aerial photo over Wilson Avenue, looking east toward 15th Street.
Above: Wilson Avenue looking east toward 15th Street 

An aerial photo of Wilson Avenue, looking west toward 3rd Street.
Above: Wilson Avenue looking west toward 3rd Street

DETOUR

Eastbound traffic on Wilson Avenue, between 9th Street and 15th Street, will be detoured at the end of July or early August. Access at 15th Street and Wilson Avenue will be maintained through October. Access remains open to all businesses.

A map depict the site under construction (westbound traffic only) on Wilson Ave, between 9th St. & 15th St, and the eastbound traffic detour using 9th St., Franklin Ave., 10th St., Bear Creek Rd., and 15th St.

An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic. 

GENERAL PROJECT NOTES

  • Access to all area businesses along the construction area will be maintained.
  • Please do not enter the construction zone before, during, or after hours.
  • Daytime work hours are in effect from 7:00 AM – 6:00 PM.

PROJECT COMMUNICATIONS

  • EMS, buses, and many other delivery/service providers have been included on this distribution list.
  • Please help us spread the word to your clients, customers, and delivery personnel regarding detouring and closures.
  • Share the project website information (provided below), where others can also sign up for updates.
  • Please contact the project team if you are not the correct contact for your organization or if others need to be included. 

QUESTIONS OR COMMENTS?

Project Websitewww.bendoregon.gov/wilson

24-Hour Construction Phone Line: (541) 322-9919

Project Contacts

The Wilson Avenue Corridor Project is the first Transportation General Obligation (GO) Bond project approved by voters in 2020. 

To learn about more projects around Bend included in the GO Bond, visit www.bendoregon.gov/gobond.