SW Sewer Basin Phase 2B Project Update – February 14, 2022

SAFETY FIRST

Please be aware of construction activities and drive carefully through the work zone, including open-trench excavation. Open trenches are fenced off at the end of each day.

CONSTRUCTION UPDATE  

Week of February 14-18 Construction Activities

  • Crews will continue installing sewer pipe and maintenance holes along McMullin Drive. This activity includes road closures and detours.
  • Crews will continue excavating and installing sewer service lines towards existing pump stations that will be decommissioned along McMullin Drive. This activity includes partial road closures and detours.

DETOURS IN EFFECT

  • A portion of McMullin Drive may be closed for excavation and sewer installation activities. Please reference the detour map below for additional information.
  • Flaggers will be present for the construction activities as needed.

A detour map depicting the work zone/road closure on a portion of McMullin Drive and the detour on Ridge Drive & Cinder Lane.An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic.

PROJECT COMMUNICATIONS

General Project Notes

  • Access to all businesses located at the end of Romaine Village Way will be maintained.
  • Emergency access will be maintained throughout construction.

QUESTIONS OR COMMENTS?

Project Website: https://www.bendoregon.gov/swsewerpipe

Project Contact: Jake Sherman, Senior Project Engineer – Phone: (541) 383-4882 | Email: jsherman@bendoregon.gov

A photo of an excavated trench with existing utilites exposed for the sewer main installation in McMullin Drive.
Above: Sewer main installation in McMullin Drive with existing utilities

A photo of work crews and excavation equipment performing excavation work for new sewer services along McMullin Drive.
Above: Excavation for new sewer services along McMullin Drive