Construction Activities – Week of July 26

  • Crews will continue backfilling and surface finish work on the substructure “bent” units that support the BNSF bridge overcrossing. 
  • Work on the Mechanically Stabilized Earth (MSE) retaining walls will include procuring precast panels, setting panels, and backfilling.
  • Installation of storm drywells and maintenance holes along Murphy Road will continue.
  • Landscape and irrigation work will continue along Murphy Road.

An interactive map of closures and detours can be found online at www.bendoregon.gov/traffic.

Contact the project team with concerns, comments, and questions at (541) 322-9919.

Accommodation Information for People With Disabilities  

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic & CD formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at MurphyProjectTeam@bendoregon.gov or (541) 322-9919; Relay Users Dial 7-1-1, and (541) 385-6676. 

View All News