Murphy Corridor Improvements Project Update – May 04, 2021

Thank you for your interest in the Murphy Corridor Improvements Project.

Construction Activities – Week of May 3

  • Crews will finish street excavation and backfill work along Murphy Road.
  • Base rock will continue to be installed in preparation for paving.
  • As part of the modernization improvements, crews will continue setting forms and pouring sidewalks and driveways
  • Crews will continue preparing for irrigation and landscape improvements, including setting boulders.
  • Fence work will continue on the retaining wall along Murphy Road, west of Tapadera Street.

An interactive map of closures and detours can be found at www.bendoregon.gov/traffic

Traffic Reminder

The south and east leg of the Murphy Road/Country Club Drive roundabout are open. Murphy Road is one-way from Country Club to Parrell Road (local access only).

Westbound Detour: Take Murphy Road to Country Club Drive. Turn right on Knott Road. Turn right on China Hat Road. Turn right on Parrell Road.

Eastbound Detour: Take Murphy Road to Parrell Road. Continue on Parrell Road, turn right on Brosterhous Road, and follow to stop sign. Turn right on Brosterhous Road and follow through Brosterhous Roundabout to Murphy Road.

Please contact the project team with concerns, comments, and questions at (541) 322-9919.

Accommodation Information for People With Disabilities  

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic & CD formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at MurphyProjectTeam@bendoregon.gov or (541) 322-9919; Relay Users Dial 7-1-1, and (541) 385-6676. 

View All News