Columbia Roundabout Improvements Project Update – April 14, 2021
The Colorado Ave./Columbia St. Intersection is Closed
SAFETY FIRST
Business workers and patrons on the corners of the Colorado Avenue/Columbia Street intersection have commented on the fast-track construction schedule of this roundabout. Great observations of what is really happening out there. That said, conditions in and around the construction corridor change quickly. One constant is the detour shown below. Please continue to recognize the road closures.
CONSTRUCTION UPDATE
April 14 through April 20 – Colorado/Columbia Intersection
- Final subgrade preparation and concrete paving of the roadway begins.
- Permanent signage installation will start soon.
DETOUR
- The Colorado Avenue/Columbia Street intersection remains closed. Construction is on schedule, and the closure is anticipated to last through the middle of May.
- The following detour remains in effect.
CONSTRUCTION PHOTOS

Above: What a difference a week makes

Above: Roundabout approach and future crossing
PROJECT DESIGN
It’s really taking shape – Colorado/Columbia roundabout.
BUSINESS ACCESS
Business Access remains open on all legs of this project affected by the current detour.
Access to Mill Point, OSU-Cascades, 705-775 SE Bonnett Way, 600-650 SW Columbia, and Deschutes Ridge businesses is available by driving past this sign and through the Columbia Street/Shevlin Hixon Intersection.
QUESTIONS OR COMMENTS?
Project Website: www.bendoregon.gov/columbia-roundabouts
Project Phone Line: (458) 256-6009
Project Contacts:
George Franklet, City of Bend Project Engineer – gfranklet@bendoregon.gov or (541) 693-2182
Deedee Fraley, City of Bend Project Engineer – dfraley@bendoregon.gov or (541) 385-6199
Ron Hand, Project Public Involvement Coordinator – rhand@dowl.com or (541) 385-4772