North Interceptor Sewer Project Update – April 2, 2020

Thank you for your interest in the North Interceptor Sewer Line Project.

The Governor’s orders and local emergency orders have not put direct restrictions on construction activities. Work on the North Interceptor Sewer Line Project is continuing on schedule. However, our practices have changed due to required social distancing protocols.

The North Interceptor Sewer Line Project is divided into three distinct phases. Phase I is under construction and expected to be completed in October 2020. 

Upcoming Activities:

  • Installation of the mainline pipe continues with approximately 1,000 linear feet remaining.
  • The electrical rough-in will take place in the electrical building at the Water Reclamation Facility (WRF).
  • Continued construction of the wet well at the WRF.
  • Restoration of the disturbed area has begun and will continue along Gentry Loop and City property.
  • Crews have completed the restoration of the North Unit Irrigation District canal.

Phase Two:

  • Phase II design is nearing completion.
  • Guaranteed Maximum Price for construction is currently scheduled to be authorized by City Council on May 6, 2020.
  • Construction is slated to begin in June 2020. Additional construction notices specific to each work area will be sent out to properties along the alignment prior to construction. See the graphic below for Phase II segments.
    • Segment 1 Construction – Scheduled to begin Summer 2020 (6-12 month duration)
    • Segment 2 Construction – Scheduled to begin Summer 2020 (6-12 month duration)
    • Segment 3 Construction – Scheduled to begin Fall 2020 (6-12 month duration)
    • Overall Phase II Project Completion – Anticipated Winter 2021/2022
  • Additional information regarding the Juniper Ridge Construction Zone, including Frequently Asked Questions, can be found at www.bendoregon.gov/north-interceptor.

An exhibit depicting the approximate boundaries in correlation with Phase II, Segments 1-3.
Above: Exhibit depicting approximate limits of Phase II, Segments 1-3

Thank you for your patience and cooperation during the design and construction of this important infrastructure project.

If you have questions or concerns, please call the project team at (541) 382-3264 or visit our project website at www.bendoregon.gov/north-interceptor. 

A photo of the wet well, electrical building, work crews, and excavation equipment on a construction site at the Water Reclamation Facility.
Above: The wet well (foreground) and electrical building (background) at the Water Reclamation Facility

Accommodation Information for People with Disabilities

Sign language interpreter service, assistive listening devices, materials in alternate formats such as Braille, large print, electronic formats and CD Formats, or any other accommodations are available upon advance request. To obtain this information, please contact the project team at northinterceptorinfo@bendoregon.gov or (541) 382-3264; Relay Users Dial 7-1-1, and (541) 385-6676.

View All News