Galveston Corridor Safety Project Update
We want to share a brief update on the Galveston Corridor Safety Project.
Phase 1
Replacing driveway and alley approaches on Galveston Avenue was done in August.
Phase 2
The Phase 2 raised crossing at 17th Street to calm traffic and a water system pressure-reducing valve project in the same area is going to be re-bid in coming days and is anticipated for construction this winter.
The City Council had approved a contract for Phase 2 of the project on October 21, but due to some technical contractual issues, the City needs to rebid the plan. We expect to return to the City Council for a new contract approval in December. Because of this, the Phase 2 construction work that was anticipated for this fall will shift into early 2027.
Seasonal weather conditions can impact asphalt and concrete work and can always be a factor in construction scheduling.
Phase 3
In response to community feedback, the updated Phase 3 design will include a new rapid flashing beacon and additional striping at the intersection of Galveston Avenue and Columbia Avenue. Final designs are being completed and will be advertised for bid next. Phase 3 includes the biggest set of upgrades, with significant improvements to enhance safety, accessibility, and pavement conditions.
We understand that project schedules affect businesses, residents, and everyone who travels through the corridor. Thank you for your continued patience and support as we work toward delivering these important safety, accessibility, and roadway improvements for the community.
Learn more about all phases at bendoregon.gov/galveston