Midtown Crossings Project Update

Hawthorne Bridge rendering at night.

Hawthorne Crossing Open House

Thursday, Dec. 3, 2026, 4:30-7 p.m.
Open Space Studios, 220 NE Lafayette Ave

A virtual open house is available now through Dec. 10 at direc.to/nvj6.

You are invited to attend an open house on Thursday, Dec. 3, 4:30-7 p.m. at Open Space Event Studios, 220 NE Lafayette Ave, Bend. The event will include the latest design for the new pedestrian and bicycle bridge, updates made based on community input and technical analysis, and an overview of the project’s next steps and timeline. Since last fall, ODOT and the City of Bend have worked with consultants to refine the bridge design, and the near final details are now ready to share with the community. The updated designs include new landing details and street connections, as well as some aesthetic features.

Learn More


Franklin Avenue Underpass is Temporarily Open for the Holiday Season

Looking west through the Franklin Street undercrossing.

The Franklin Avenue undercrossing is temporarily open through January 3 to help improve holiday travel and access to local businesses during the holiday shopping season. While the underpass is open to traffic, construction continues in other areas of the project corridor. Please continue to use caution when traveling in the area and follow posted signs.

What to Expect During the Temporary Opening:

  • The new bike climbing lanes will not be installed yet, so cyclists will continue to merge with traffic or use the sidewalk.
  • The south undercrossing sidewalk will be open for bikes and pedestrians.
  • Construction continues in other areas of the project.
  • Use extra caution when traveling in the area and follow posted signs.
  • Turns from Franklin Avenue onto Hill Street are not permitted.

Underpass Closure Will Resume Monday, January 4

On Monday, January 4, 2027, work will resume in the underpass with full closure of Franklin Avenue from Harriman Street to First Street. Detour routes will resume on Third Street, Greenwood Avenue, and Wall and Bond streets. Olney Avenue and Colorado Avenue will also be fully accessible during the undercrossing closure. Link to detour map.

  • Emergency response access will be maintained at all times.
  • Access to all businesses will be open throughout construction. Follow posted business access signs.
  • One side of the undercrossing sidewalk path will remain open for pedestrians and cyclists.

The project remains on schedule for completion by the end of May.


Midtown Crossings Project

The Midtown Crossings Project is improving east-west travel between downtown and the Central District and includes improvements to four key connections in the area: Greenwood Avenue, Hawthorne Avenue, Franklin Avenue and Second Street.

Sign up for project updates at bendoregon.gov/midtowncrossings.


GO Bond Dashboard

This project is funded in part by the 2020 Transportation GO Bond.

To keep things transparent and accountable, the Transportation Bond Oversight Committee created the GO BOND Dashboard. It gives you easy access to the latest GO Bond projects and is updated with financial information every quarter.

Learn more


Questions or Comments?

Construction Phone Line: 541-323-0771
Project website: bendoregon.gov/midtowncrossings
Project e-mail: midtownxings@bendoregon.gov

Project Contact:

Todd Johnson, Project Engineer