Project Status

Plan
Design
Build
Complete

Contact

Jefferson Place Water Line Replacement

PROJECT UPDATE JULY 28, 2026

Water utility work has advanced to NW Adams Place. Crews completed installation of the new water main and water services along NW Delaware Avenue, from NW Broadway Street to the intersection of Adams Place and Delaware Avenue, on July 24. Paving of this section of Delaware is planned the week of Aug. 4, 2026 and is expected to take one to two days. The roadway will be closed to parking and travel during paving operations and is expected to open to traffic by the evening on paving days. Residents will be notified 24 hours in advance of closure.

Crews expect to complete water main installation along Adams Place by mid-August. Once installation is complete, the new water main will be connected to the existing system, requiring a temporary water service interruption for nearby customers. Affected properties will receive notice at least 48 hours before any planned outage.

After crews complete the work on Adams Place, they will begin the final phase of the project on Delaware Avenue from the Adams Place intersection to the alley between NW Shasta Place and NW Jefferson Place.

The project remains on schedule for completion by the end of September.

Location

Estimated Schedule

What to Expect During Construction

Funding