PROJECT UPDATE AUGUST 13, 2026

Phase 3 of the water main improvements on NW Adams Place is progressing well, with installation of the new water main now complete. Over the next several days, water service will be transferred from the temporary system to the new water main.

Paving of Adams Place is scheduled for late agosto and is expected to take one to two days. Residents will receive door hanger notifications at least 24 hours before paving operations begin. Paving will require a full closure of Adams Place, and on-street parking will not be permitted during construction activities.

The project’s fourth and final phase will then advance west along NW Delaware Avenue to the alley intersection between NW Shasta Place and NW Jefferson Place. Work in this area will include water main installation, service connections and roadway restoration.

The project remains on schedule to be completed by the end of septiembre 2026. Thank you for your continued patience as we complete these important infrastructure improvements.